Report Date - 27 FEBRUARY 2004
A - Steam Power Stations
Power StationsType FuelNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget Load MWRemarks
123456
DibisNatural Gas41x724
BaijiFuel Oil64xxxx297500#6 start of operation
DauraFuel Oil40180#3 trip drum level low
South BaghdadFuel Oil63xxx60200#3 leak in boiler
MussaibeCrude and Fuel Oil41x220860#2 problem in thrust bearing
NassiryaCrude44xxxx580600#1 start of operation
NajebiaNatural Gas and Crude21x90160#5 loss of auxilary
HarthaNatural Gas and Crude42xx200300
Out of Service for Unscheduled MaintanenceTotal:1,4542,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations Report Date - 27 FEBRUARY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 1 x 7 24 Baiji Fuel Oil 6 4 x x x x 297 500 #6 start of operation Daura Fuel Oil 4 0 180 #3 trip drum level low South Baghdad Fuel Oil 6 3 x x x 60 200 #3 leak in boiler Mussaibe Crude and Fuel Oil 4 1 x 220 860 #2 problem in thrust bearing Nassirya Crude 4 4 x x x x 580 600 #1 start of operation Najebia Natural Gas and Crude 2 1 x 90 160 #5 loss of auxilary Hartha Natural Gas and Crude 4 2 x x 200 300 Out of Service for Unscheduled Maintanence Total: 1454 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Report Date - 27 FEBRUARY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 135 125 Gas Oil Musil Dam Main 4 4 570 600 Quds 2 2 5 160 Gas Oil Musil Dam reg 4 3 22 60 Mosil 12 10 153 150 Musil Pumping 2 0 Dibis 3 2 55 30 Haditha Dam 6 160 Old Mulla 12 7 109 128 Samarra 3 3 48 55 New Mulla 6 4 138 173 Himrin 2 2 50 21 Taji 7 55 Hindia 4 3 6 5 M. Taji 2 18 Kufa 4 1 1 0 Daura 4 30 Total 697 896 Hilla 4 2 34 64 System Generation MWh Najaf 3 2 100 129 Syrian Line Generation MWh Khor 4 3 80 80 Natural Gas Turkey Line Generation MWh Shuaiba 2 1 120 20 Natural Gas Total Generation 94097 MWh M. Shuaiba 2 Natural Gas split with the refinery System Peak Load 3654 MW Petro 4 0 Natural Gas Syria Peak Load 60 MW M. Dibis 4 24 Natural Gas Turkey Peak Load 80 MW Mossil East 5 0 Gas Oil Fixed Gen Peak Load 266 MW Hmam/Zafranya 7 10 Gas Oil Total Peak Load 4060 MW Diesel Gas Oil Baghdad Load 1460 MW Total 939 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Report Date - 27 FEBRUARY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1377 Duhok 60 Naynawa 278 Tamim 123 Salah Aldeen 175 Anbar 163 Dyala 78 Babil 111 Kirbala 104 Najaf 109 Kadsya 85 Wasit 50 Muthana 53 Nasirya 122 Misan 51 Basra 320