Report Date - 13 FEBRUARY 2004
A - Steam Power Stations
Power StationsType FuelNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget Load MWRemarks
123456
DibisNatural Gas42881624
BaijiFuel Oil6485858585340500
DauraFuel Oil413030180
South BaghdadFuel Oil617070200
MussaibeCrude and Fuel Oil43200200200600860
NassiryaCrude44155150150150605600
NajebiaNatural Gas and Crude21100100160
HarthaNatural Gas and Crude428090170300
Out of Service for Unscheduled MaintanenceTotal:1,9312,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations Report Date - 13 FEBRUARY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 2 8 8 16 24 Baiji Fuel Oil 6 4 85 85 85 85 340 500 Daura Fuel Oil 4 1 30 30 180 South Baghdad Fuel Oil 6 1 70 70 200 Mussaibe Crude and Fuel Oil 4 3 200 200 200 600 860 Nassirya Crude 4 4 155 150 150 150 605 600 Najebia Natural Gas and Crude 2 1 100 100 160 Hartha Natural Gas and Crude 4 2 80 90 170 300 Out of Service for Unscheduled Maintanence Total: 1931 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Report Date - 13 FEBRUARY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 130 125 Gas Oil Musil Dam Main 4 600 Quds 2 2 220 160 Gas Oil Musil Dam reg 4 60 Mosil 12 10 155 150 Musil Pumping 2 0 Dibis 3 2 57 30 Haditha Dam 6 160 Old Mulla 12 6 80 128 Samarra 3 55 New Mulla 6 4 135 173 Himrin 2 21 Taji 7 4 70 55 Hindia 4 5 M. Taji 2 18 Kufa 4 0 Daura 4 3 70 30 Total 0 896 Hilla 4 3 34 64 System Generation MWh Najaf 3 2 95 129 Syrian Line Generation MWh Khor 4 2 80 80 Natural Gas Turkey Line Generation MWh Shuaiba 2 6 6 20 Natural Gas Total Generation MWh M. Shuaiba 2 Natural Gas System Peak Load MW Petro 4 1 10 0 Natural Gas Syria Peak Load MW M. Dibis 4 3 10 24 Natural Gas Turkey Peak Load MW Mossil East 5 3 16 0 Gas Oil Fixed Gen Peak Load MW Hmam/Zafranya 7 3 51 Gas Oil Total Peak Load MW Diesel Gas Oil Baghdad Load MW Total 1219 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Report Date - 13 FEBRUARY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1700 Duhok 80 Naynawa 400 Tamim 151 Salah Aldeen 230 Anbar 202 Dyala 118 Babil 110 Kirbala 128 Najaf 135 Kadsya 70 Wasit 100 Muthana 65 Nasirya 130 Misan 65 Basra 270