DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 23, 2004

التاريخ
23 آذار 2004
الفئة
الخدمات الأساسية
النص متوفر
الإنكليزية
عدد الملفات
1
الأصل الإنكليزي DOCتنزيل النص الإنكليزي
DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 23, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: We will continue to see decreased power as we enter into the spring maintenance period. Sabotage will continue to have unanticipated and detrimental effects on power output. Generation: Peak Power 4016Mw, 89,940Mw hours, 7-day Avg. 4132Mw Generators Returned to Service: 170 Mw Baiji 2, CP 110 Mw Hilla 3 20 Mw Khor Zubayr 4 40 Mw Generators Unscheduled Out of Service (19) 598Mw PLANT Type SP, CP, RP, HP Fault Mw * Dibis 3 SP Feed water pump 8 Baiji 4 SP High water Consumption 90 * South Baghdad 4 SP Boiler Leak 30 South Baghdad 5 SP Air Heater 30 Nassirya 4 SP Turbine 125 Najebia 4 SP Oil Leak 90 Mosil 1 CP Rotor Defect 15 * Mosil 8 CP Emergency stop 15 Mosil 9 CP Rotor Defect 15 Mosil 11 CP Hydraulic Pressure 15 Old Mulla 1 CP Acc Gear 15 Old Mulla 2 CP Servo 15 Old Mulla 8 CP Vibrations 15 Old Mulla 5 CP Inlet Valve 15 Old Mulla 9,10 CP Transformer damage 30 New Mulla 6 CP Generator Defect 30 Taji 3, CP Compressor 15 Taji 4 CP Control card 15 Taji Mobile, 2 CP Software problem 15 * RED – Denotes out of service since last report Generators Scheduled Out of Service (21) 1478 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 1 SP M TBD 21 Mar 04 21 May 100 Baiji 3 SP M Bechtel 29 Feb 04 1 May 100 Dibis 4 SP M ME 15 Mar 04 30 Apr 8 Doura 2 CP M ME 21 Feb 04 15 May 20 Doura 3 CP R TBD 1 Mar 03 20 Doura 4 SP M ME 2 Feb 04 20 Apr 65 Doura 5 SP R Bechtel Jul 03 30 May 100 Doura 6 SP R Bechtel Jul 03 30 Jun 100 Dibis 3 SP M GRD-RIE 30Dec 03 1 Aug 110 Dibis 4 CP R GRD/RIE Sep 03 1 Sep 110 Khor Zubayr 2 CP M GRD/RIE 15 Mar 04 21 May 50 Mosil 2 CP M ME 21 Mar 04 TBD 15 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Mussaibe 4 SP M ME 7 Feb 04 15 May 200 Nassirya 2 SP M ME 9 Mar 04 15 Apr 150 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 Shuaiba 1 CP M ME 14 Feb 04 31 May 20 South Baghdad 1 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 2 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 3 SP R ME 18 Mar 04 18 May 20 Taji 7 CP R GRD/RIE 1 Oct 03 15 May 15 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 102 towers complete/212req’d Haditha-Baghd West 400 Sabotage GRD/RIE 15 Apr 246 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE Complete 297 towers complete/297 req’d Baiji - Baghd West #1 400 Sabotage GRD/RIE 31 Mar 68 towers complete/68 req’d Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 30 May Dibis/Irbil-Quarqush 132 New Line GRD/RIE 15 May Dibis to Old Kirkuk 132 Reconductor GRD-RIE 15 Jun Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE 15 Jun Bids for work under evaluation Jazair to Yarmook 132 Reconductor GRD-RIE 15 Jun Bids for work under evaluation Baghd West – Jamia 132 Sabotage ME TBD Al Amarah-Burzulgan 132 Looting GRD-RIE 15 Jun 26 towers complete /126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: None reported today Distribution: Report Date -23 MARCH 2004 Power transferred from North to Middle 780 MW. Power transferred from South to Middle 85 MW. GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1380 29948 1248 Duhok 80 1924 80 Naynawa 335 8723 363 Tamim 140 3253 136 Salah Aldeen 210 5339 222 Anbar 205 5052 211 Dyala 100 2626 109 Babil 110 2715 113 Kirbala 94 2144 89 Najaf 115 2690 112 Kadsya 70 1516 63 Wasit 90 2178 91 Muthana 59 1474 61 Nasirya 120 2721 113 Misan 65 1510 63 Basra 275 5985 248 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 3 of NUMPAGES 3