DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 19, 2004

التاريخ
19 نيسان 2004
الفئة
الخدمات الأساسية
النص متوفر
الإنكليزية
عدد الملفات
1
الأصل الإنكليزي DOCتنزيل النص الإنكليزي
DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 19, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: Nassirya 3and 4 synchronizing with the system, not producing at capacity now. Shuaiba 2 returned from programmed maintenance. We will continue to see decreased power as we progress through the spring maintenance period. Generation: Peak Power 3496Mw, 75, 542Mw hours, 7-day Avg. 3602Mw Turkish Region Average Generation 162.9 Mw (not included in Peak Power) Generators Returned to Service: (8) 290 Mw South Baghdad 5 30 Mw Nassirya 3 60 Mw Nassirya 4 100 Mw Baiji Mobile, 1,2,3 75 Mw Mosil 11 15 Mw Shuaiba 2 10 Mw Generators Unscheduled Out of Service (21) 818 Mw PLANT Type SP, CP, RP, HP Fault Mw Dibis 2 SP Boiler Leak 8 South Baghdad 6 SP Boiler leak 30 * Hartha 4 SP Furnace leak 180 Baiji 1 CP Filter Cleaning 85 Baiji Mobile, 4 CP No Fuel Filters 100 * Khor Zubayr 4 CP Flame loss 50 * Khor Zubayr 1 CP Bleeder valve problem 50 Qudas 2 CP Control card problems 90 Mosil 1 CP Rotor Defect 15 Mosil 2 CP Load Gear Oil leak 15 Mosil 9 CP Rotor Defect 15 Old Mulla 1 CP Acc Gear 15 Old Mulla 6 CP High exhaust temperature 15 Old Mulla 7 CP Generator Vibrations 15 Old Mulla 9 CP Load gear problems 15 Old Mulla 10 CP Vibrations 15 New Mulla 3 CP Load gear oil leak 30 New Mulla 4 CP Load gear oil leak 30 Taji 3, CP Compressor 15 Taji 5 CP Excitor problem 15 M. Taji 2 CP Software 15 RED – Denotes out of service since last report Generators Scheduled Out of Service (24) 1608 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 1 SP M TBD 21 Mar 04 15 May 100 Baiji 3 SP M Bechtel 29 Feb 04 20 Apr 100 Dibis 4 SP M ME 15 Mar 04 30 Apr 8 Doura 4 CP M ME 14 Apr 04 TBD 20 Doura 3 CP R GRD/RIE 1 Mar 03 TBD 20 Doura 3 SP M ME 18 Mar 04 18 May 65 Doura 4 SP M ME 2 Feb 04 20 Apr 65 Doura 5 SP R Bechtel Jul 03 20 Jun 100 Doura 6 SP R Bechtel Jul 03 20 Jul 100 Dibis 4 CP R GRD/RIE Sep 03 12 May 30 Hartha 1 SP M ME 22 Mar 04 23 May 100 Khor Zubayr 2 CP R GRD/RIE 15 Mar 04 15 Jun 50 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Mussaibe 4 SP M ME 7 Feb 04 30 Apr 200 Nassirya 1 SP M ME 30 Mar 04 15 May 130 Nassirya 2 SP M ME 9 Mar 04 15 Apr 150 New Mulla 6 CP R GRD/RIE 28 Mar 04 15 May 30 Old Mulla 8 CP M ME 17 Apr 04 TBD 15 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 South Baghdad 1 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 2 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 3 SP R ME 18 Mar 04 18 May 20 Taji 7 CP R GRD/RIE 1 Oct 03 15 May 15 Taji 6 CP M ME 2 Apr 04 TBD 15 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 102 towers complete/212req’d Haditha-Baghd West 400 Sabotage GRD/RIE Complete 246 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE Complete MoE completing PLC work Baiji - Baghd West #1 400 Sabotage GRD/RIE Complete Operational Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 15 Jun Dibis/Erbil-Qara Qosh 132 New Line GRD/RIE 15 May Contractor mobilized Dibis to Old Kirkuk 132 Reconductor GRD-RIE 15 Jun Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Jazair to Yarmook 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Baghd West – Jamia 132 Sabotage ME TBD Al Amarah-Burzulgan 132 Looting GRD-RIE 15 Jun 26 towers complete /126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: Distribution: Power transferred from North to Middle 900 MW. Power transferred from South to Middle -200 MW. GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1190 24186 1008 1439 Duhok 80 1918 80 113 Naynawa 270 6480 270 526 Tamim 120 2991 125 177 Salah Aldeen 210 4673 195 246 Anbar 175 4199 175 227 Dyala 70 1625 68 132 Babil 90 1974 82 140 Kirbala 65 1936 81 104 Najaf 145 2311 96 127 Kadsya 50 1291 54 88 Wasit 80 1836 77 124 Muthana 55 1280 53 74 Nasirya 90 2422 101 118 Misan 65 1558 65 83 Basra 250 6011 250 262 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 1 of NUMPAGES 3