الرئيسية / الخدمات الأساسية / ESS-d7eebb18

الخدمات الأساسية

DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 9, 2004

التاريخ
9 آذار 2004
الفئة
الخدمات الأساسية
النص متوفر
الإنكليزية
عدد الملفات
1
الأصل الإنكليزي DOCتنزيل النص الإنكليزي
DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 9, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: We will continue to see decreased power as we enter into the spring maintenance period. Sabotage will continue to have unanticipated and detrimental effects on power output. Generation: Peak Power 4003Mw, 84,684Mw hours, 7-day Avg. 3904Mw Generators Returned to Service: 93 Mw Dibis 2 8 Mw Qudas 2 50 Mw Hilla 1 20 Mw Dibis 6, CP 15 Mw Generators Unscheduled Out of Service 578 Mw PLANT Type SP, CP, RP, HP Fault Mw Dibis 1 SP Boiler Leak 8 * South Baghdad 3 SP Generator Differential 30 Najebia 4 SP Valve Leak 90 Hartha 4 SP Boiler Leak 90 Baiji 1 CP Lubricating oil leak 110 Khor Zubayr 4 CP Generator Protector 50 Mosil 1 CP Rotor Defect 15 Mosil 9 CP Rotor Defect 15 Mosil 11 CP Hydraulic Pressure 15 Najaf 2 CP Vibrations 50 Old Mulla 1 CP Acc Gear 15 Old Mulla 2 CP Servo 15 New Mulla 6 CP Generator Defect 30 Taji 3, CP Compressor 15 Taji 4 CP Control card 15 Taji Mobile, 2 CP Software problem 15 * RED – Denotes out of service since last report Generators Scheduled Out of Service 1291 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 2 SP M Bechtel 2 Jan 04 9 Mar 100 Baiji 3 SP M GRD/RIE 29 Feb 04 1 May 100 Doura 2 CP M ME 21 Feb 04 TBD 20 Doura 3 CP R GRD/RIE 1 Mar 03 15 May 20 Doura 4 SP M ME 2 Feb 04 20 Apr 65 Doura 5 SP R Bechtel Jul 03 30 Apr 100 Doura 6 SP R Bechtel Jul 03 31May 100 Dibis 3 SP M ME 30Dec 03 31 May 8 Dibis 4 CP R GRD/RIE Sep 03 1 May 18 Hilla 2 CP M ME 9 Mar 04 TBD 20 Hilla 3 CP M ME 9 Mar 04 TBD 20 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Mussaibe 4 SP M ME 7 Feb 04 7 Mar 200 Nassirya 2 SP M ME 9 Mar 04 TBD 150 New Mulla 2 CP M ME 17 Feb04 TBD 30 Old Mulla 5 CP M GRD/RIE 1 Nov 03 15 May 15 Old Mulla 8 CP M GRD/RIE 28 Feb 04 15 May 15 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 Taji 7 CP R GRD/RIE 1 Oct 03 15 May 15 Shuaiba 1 CP M ME 14 Feb 04 31 May 20 South Baghdad 1 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 2 SP M ME 12 Feb 04 12 Apr 30 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 102 towers complete/212req’d Haditha-Baghd West 400 Sabotage GRD/RIE 15 Apr 143 towers complete/236 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE 8 Mar 294 towers complete/297 req’d Baiji - Baghd West #1 400 Sabotage GRD/RIE 31 Mar 68 towers complete/68 req’d Baghd E.-Baghd S. #2 400 New Line GRD/RIE 8 Mar 81 towers complete/81req’d Haditha – Qaim 400 Sabotage ME TBD No contract awarded Baiji – Haditha 400 Sabotage ME TBD No contract awarded Diyala Connection 400 New Line ME 30 Apr Dibis/Irbil-Quarqush 132 New Line GRD/RIE 15 May Contractor on-site 20 Feb Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME TBD 44 towers complete/44 req’d Baghd West – Jamia 132 Sabotage ME TBD Omara-Burzegan 132 Looting ME 1 May 26 towers complete/126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: None reported today Distribution: Report Date -9 MARCH 2004 Power transferred from North to Middle 850 MW. Power transferred from South to Middle 200 MW. GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1370 27417 1142 Duhok 84 1964 82 Naynawa 310 10227 426 Tamim 132 3665 153 Salah Aldeen 222 5019 209 Anbar 205 4547 189 Dyala 115 2295 96 Babil 105 2273 95 Kirbala 80 2055 86 Najaf 105 2489 104 Kadsya 55 1242 52 Wasit 90 1894 79 Muthana 70 1365 57 Nasirya 135 2851 119 Misan 65 1490 62 Basra 270 6385 266 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 2 of NUMPAGES 3