# A-Steam Power Stations
REPORT DATE - 29 DECEMBER 2003
A - Steam Power Stations
Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 2 0 8 0 8 16 24 No.1 mnt 10 DEC to 25 JAN. No 3 FDF.
Baiji Fuel Oil 6 3 100 90 0 100 0 0 290 500 No. 5 rehab. No. 6 mnt 5 DEC to 19 JAN. No. 3 stopped 2220 drum level low.
Dura Fuel Oil 4 1 80 0 0 0 80 180 Nos. 5 & 6: Rehab. No. 4 stopped 1925 boiler leak.
South Baghdad Fuel Oil 6 4 35 25 0 35 0 35 130 200 No. 5 mnt 1 DEC to 15 JAN. No. 3 stopped 1930 boiler leak.
Mussaibe Crude and Fuel Oil 4 3 215 100 0 215 530 860 No. 3 program mnt.
Nassirya Crude 4 2 140 145 0 0 285 600 No. 3 mnt 11 NOV to 15 DEC. No. 4 stopped 2055 for mnt.
Najebia Natural Gas and Crude 2 0 0 0 0 160 Hartha Natural Gas and Crude 4 1 140 0 140 300 No. 4 Mnt from 23 OCT to 23 DEC.
Total: 1471 2824
# B- Gas_C-Power Stations
Report Date- 29 DECEMBER 2003 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 100 125 Gas Oil No. 2 insufficient fuel. Musil Dam Main 4 3 390 600 Quds 2 2 200 160 Gas Oil 39 trucks. Musil Dam reg 4 3 30 60 450 Mosil 12 8 121 150 30 No. 1 Rotor Defect. No. 2 servo ACC. No. 3 Prog Maint. No. 9 rotor defect. Musil Pumping 2 1 110 0 Dibis 3 1 27 60 28 No. 4 and 5 rehab. No. 6 synch. Haditha Dam 6 2 32 160 480 Old Mulla 12 6 80 128 530 No. 1 ACC gear. No. 2 servo. No. 4 tripped 2230 vibration. No. 5 Programmed Mnt. No. 6 acc gear. No. 7 programmed mnt. No. 12 rehab. Samarra 3 2 35 55 390 New Mulla 6 4 130 173 320 No. 5 programmed mnt. No. 6 Generator Defective. Himrin 2 1 22 21 Taji 7 3 58 55 18 No. 3 Compressor. No. 4 Turbine. No. 5 pilot excit. No. 7 Rehab. Hindia 4 4 5 5 M. Taji 2 1 7 20 0 No. 2 software. Kufa 4 0 0 1 Dura 4 3 70 30 16 No.3 Rehabilitation. Total 624 896 Hilla 4 4 70 64 34 System Generation 77870 MWh Najaf 3 2 100 129 31 No. 2 program mnt. Syrian Line Generation 1357 MWh Khor 4 3 120 80 Natural Gas No. 4: Rehabilitation. Turkey Line Generation 1944 MWh Shuaiba 2 1 10 20 Natural Gas No. 1 S/B Total Generation 81171 MWh Petro 4 1 10 0 Natural Gas System Peak Load 3655 MW M. Dibis 4 4 8 24 Natural Gas Syria Peak Load 20 MW Mossil East 5 4 20 15 Gas Oil Turkey Peak Load 80 MW Hmam/Zafranya 7 2 3 Gas Oil Fixed Gen Peak Load 77 MW Diesel 8 Total Peak Load 3832 MW Total 1142 1233 Baghdad Load 1500 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
GOVERNORATE Peak Load MW MWH Average Load MW 29 December, 2003 Baghdad 1500 29842 1243.4167 Power transferred from North to Middle 530 MW.
Duhok 80 1890 78.75
Naynawa 400 8180 340.8333 Power transferred from South to Middle 160 MW.
Tamim 170 3636 151.5
Salah Aldeen 200 4353 181.375 Anbar 160 3766 156.9167 Dyala 80 1851 77.125 Babil 90 1884 78.5 Kirbala 70 1616 67.3333 Najaf 90 1751 72.9583 Kadsya 70 1276 53.1667 Wasit 85 1830 76.25 Muthana 60 1141 47.5417 Nasirya 115 2574 107.25 Misan 65 1219 50.7917 Basra 300 6117 254.875 3535
الرئيسية / الخدمات الأساسية / ESS-b9cf2026
الخدمات الأساسية
Power System 29 dec
- التاريخ
- 29 كانون الأول 2003
- الفئة
- الخدمات الأساسية
- النص متوفر
- الإنكليزية
- عدد الملفات
- 1
معاينة الجدول
الورقة «A-Steam Power Stations»: 13 صفاً × 13 عموداً
| REPORT DATE - 29 DECEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load | Remarks | |||||
| Fuel | 1 | 2 | 3 | 4 | 5 | 6 | MW | |||||
| Dibis | Natural Gas | 4 | 2 | 0 | 8 | 0 | 8 | 16 | 24 | No.1 mnt 10 DEC to 25 JAN. No 3 FDF. | ||
| Baiji | Fuel Oil | 6 | 3 | 100 | 90 | 0 | 100 | 0 | 0 | 290 | 500 | No. 5 rehab. No. 6 mnt 5 DEC to 19 JAN. No. 3 stopped 2220 drum level low. |
| Dura | Fuel Oil | 4 | 1 | 80 | 0 | 0 | 0 | 80 | 180 | Nos. 5 & 6: Rehab. No. 4 stopped 1925 boiler leak. | ||
| South Baghdad | Fuel Oil | 6 | 4 | 35 | 25 | 0 | 35 | 0 | 35 | 130 | 200 | No. 5 mnt 1 DEC to 15 JAN. No. 3 stopped 1930 boiler leak. |
| Mussaibe | Crude and Fuel Oil | 4 | 3 | 215 | 100 | 0 | 215 | 530 | 860 | No. 3 program mnt. | ||
| Nassirya | Crude | 4 | 2 | 140 | 145 | 0 | 0 | 285 | 600 | No. 3 mnt 11 NOV to 15 DEC. No. 4 stopped 2055 for mnt. | ||
| Najebia | Natural Gas and Crude | 2 | 0 | 0 | 0 | 0 | 160 | |||||
| Hartha | Natural Gas and Crude | 4 | 1 | 140 | 0 | 140 | 300 | No. 4 Mnt from 23 OCT to 23 DEC. | ||||
| Total: | 1,471 | 2,824 |
الورقة «B- Gas_C-Power Stations»: 25 صفاً × 13 عموداً
| Report Date- 29 DECEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 100 | 125 | Gas Oil | No. 2 insufficient fuel. | Musil Dam Main | 4 | 3 | 390 | 600 | |
| Quds | 2 | 2 | 200 | 160 | Gas Oil | 39 trucks. | Musil Dam reg | 4 | 3 | 30 | 60 | 450 |
| Mosil | 12 | 8 | 121 | 150 | 30 | No. 1 Rotor Defect. No. 2 servo ACC. No. 3 Prog Maint. No. 9 rotor defect. | Musil Pumping | 2 | 1 | 110 | 0 | |
| Dibis | 3 | 1 | 27 | 60 | 28 | No. 4 and 5 rehab. No. 6 synch. | Haditha Dam | 6 | 2 | 32 | 160 | 480 |
| Old Mulla | 12 | 6 | 80 | 128 | 530 | No. 1 ACC gear. No. 2 servo. No. 4 tripped 2230 vibration. No. 5 Programmed Mnt. No. 6 acc gear. No. 7 programmed mnt. No. 12 rehab. | Samarra | 3 | 2 | 35 | 55 | 390 |
| New Mulla | 6 | 4 | 130 | 173 | 320 | No. 5 programmed mnt. No. 6 Generator Defective. | Himrin | 2 | 1 | 22 | 21 | |
| Taji | 7 | 3 | 58 | 55 | 18 | No. 3 Compressor. No. 4 Turbine. No. 5 pilot excit. No. 7 Rehab. | Hindia | 4 | 4 | 5 | 5 | |
| M. Taji | 2 | 1 | 7 | 20 | 0 | No. 2 software. | Kufa | 4 | 0 | 0 | 1 | |
| Dura | 4 | 3 | 70 | 30 | 16 | No.3 Rehabilitation. | Total | 624 | 896 | |||
| Hilla | 4 | 4 | 70 | 64 | 34 | System Generation | 77,870 | MWh | ||||
| Najaf | 3 | 2 | 100 | 129 | 31 | No. 2 program mnt. | Syrian Line Generation | 1,357 | MWh | |||
| Khor | 4 | 3 | 120 | 80 | Natural Gas | No. 4: Rehabilitation. | Turkey Line Generation | 1,944 | MWh | |||
| Shuaiba | 2 | 1 | 10 | 20 | Natural Gas | No. 1 S/B | Total Generation | 81,171 | MWh | |||
| Petro | 4 | 1 | 10 | 0 | Natural Gas | System Peak Load | 3,655 | MW | ||||
| M. Dibis | 4 | 4 | 8 | 24 | Natural Gas | Syria Peak Load | 20 | MW | ||||
| Mossil East | 5 | 4 | 20 | 15 | Gas Oil | Turkey Peak Load | 80 | MW | ||||
| Hmam/Zafranya | 7 | 2 | 3 | Gas Oil | Fixed Gen Peak Load | 77 | MW | |||||
| Diesel | 8 | Total Peak Load | 3,832 | MW | ||||||||
| Total | 1,142 | 1,233 | Baghdad Load | 1,500 | MW | |||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
الورقة «Peak Loads»: 21 صفاً × 5 أعمدة · المعاينة لأول 19 صفاً؛ الملف الكامل من زر الأصل
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | 29 December, 2003 |
|---|---|---|---|---|
| Baghdad | 1,500 | 29,842 | 1,243.42 | Power transferred from North to Middle 530 MW. |
| Duhok | 80 | 1,890 | 78.75 | |
| Naynawa | 400 | 8,180 | 340.83 | Power transferred from South to Middle 160 MW. |
| Tamim | 170 | 3,636 | 151.50 | |
| Salah Aldeen | 200 | 4,353 | 181.38 | |
| Anbar | 160 | 3,766 | 156.92 | |
| Dyala | 80 | 1,851 | 77.12 | |
| Babil | 90 | 1,884 | 78.50 | |
| Kirbala | 70 | 1,616 | 67.33 | |
| Najaf | 90 | 1,751 | 72.96 | |
| Kadsya | 70 | 1,276 | 53.17 | |
| Wasit | 85 | 1,830 | 76.25 | |
| Muthana | 60 | 1,141 | 47.54 | |
| Nasirya | 115 | 2,574 | 107.25 | |
| Misan | 65 | 1,219 | 50.79 | |
| Basra | 300 | 6,117 | 254.88 | |
| 3,535 |