الرئيسية / الخدمات الأساسية / ESS-a91d872b

الخدمات الأساسية

DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 16, 2004

التاريخ
16 آذار 2004
الفئة
الخدمات الأساسية
النص متوفر
الإنكليزية
عدد الملفات
1
الأصل الإنكليزي DOCتنزيل النص الإنكليزي
DAILY POWER SYSTEM HIGHLIGHTS FOR MARCH 16, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: Hartha 1,4, SP and Najebia 4,5, SP operating at reduced loads due to load flow problems. We will continue to see decreased power as we enter into the spring maintenance period. Sabotage will continue to have unanticipated and detrimental effects on power output. Generation: Peak Power 4137Mw, 90,983Mw hours, 7-day Avg. 4083Mw Generators Returned to Service: 296 Mw Dibis 1, SP 8 Mw Dibis 2, SP 8 Mw South Baghdad 5 30 Mw Mussaibe 1 200 Mw Khor Zubayr 4 50 Mw Generators Unscheduled Out of Service 343 Mw PLANT Type SP, CP, RP, HP Fault Mw Dibis 4 SP Fuel Filters 8 South Baghdad 3 SP Generator Differential 30 * South Baghdad 4 SP Servo 30 Baiji 2 CP Heavy Oil commissioning 110 Mosil 1 CP Rotor Defect 15 Mosil 9 CP Rotor Defect 15 Mosil 11 CP Hydraulic Pressure 15 Old Mulla 1 CP Acc Gear 15 Old Mulla 2 CP Servo 15 Old Mulla 8 CP Vibrations 15 New Mulla 6 CP Generator Defect 30 Taji 3, CP Compressor 15 Taji 4 CP Control card 15 Taji Mobile, 2 CP Software problem 15 * RED – Denotes out of service since last report Generators Scheduled Out of Service 1291 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 2 SP M Bechtel 2 Jan 04 22 Mar 100 Baiji 3 SP M Bechtel 29 Feb 04 1 May 100 Doura 2 CP M ME 21 Feb 04 15 May 20 Doura 3 CP R GRD/RIE 1 Mar 03 15 May 20 Doura 4 SP M ME 2 Feb 04 20 Apr 65 Doura 5 SP R Bechtel Jul 03 30 Apr 100 Doura 6 SP R Bechtel Jul 03 31May 100 Dibis 3 SP M ME 30Dec 03 31 May 8 Dibis 4 CP R GRD/RIE Sep 03 1 May 18 Hilla 3 CP M ME 9 Mar 04 TBD 20 Khor Zubayr 2 CP M GRD/RIE 15 Mar 04 21 May 50 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Mussaibe 4 SP M ME 7 Feb 04 15 May 200 Nassirya 2 SP M ME 9 Mar 04 15 Apr 150 New Mulla 2 CP M ME 17 Feb04 TBD 30 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 Taji 7 CP R GRD/RIE 1 Oct 03 15 May 15 Shuaiba 1 CP M ME 14 Feb 04 31 May 20 South Baghdad 1 SP M ME 12 Feb 04 12 Apr 30 South Baghdad 2 SP M ME 12 Feb 04 12 Apr 30 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 102 towers complete/212req’d Haditha-Baghd West 400 Sabotage GRD/RIE 15 Apr 216 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE Complete 297 towers complete/297 req’d Baiji - Baghd West #1 400 Sabotage GRD/RIE 31 Mar 68 towers complete/68 req’d Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage ME TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 30 May Dibis/Irbil-Quarqush 132 New Line GRD/RIE 15 May Notice to proceed issued 12 Mar Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Baghd West – Jamia 132 Sabotage ME TBD Omara-Burzegan 132 Looting ME 1 May 26 towers complete/126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: None reported today Distribution: Report Date -16 MARCH 2004 Power transferred from North to Middle 850 MW. Power transferred from South to Middle 170 MW. GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1500 30904 1288 Duhok 70 1851 77 Naynawa 350 8518 355 Tamim 140 3376 141 Salah Aldeen 230 5199 217 Anbar 205 4902 204 Dyala 110 2624 109 Babil 120 2569 107 Kirbala 80 1919 80 Najaf 117 2585 108 Kadsya 65 1618 67 Wasit 90 2067 86 Muthana 90 1829 76 Nasirya 120 2702 113 Misan 70 1560 65 Basra 305 6641 277 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 2 of NUMPAGES 3