Reporting Peak for 06 MAY 2004 / Report Date - 07 MAY 2004
A - Steam Power Stations
Power StationsType FuelNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget Load MWRemarks
123456
DibisNatural Gas4x924
BaijiFuel Oil6x100500
DauraFuel Oil40180
South BaghdadFuel Oil6xxx85200
MussaibeCrude and Fuel Oil4xx415860
NassiryaCrude4xxx445600
NajebiaNatural Gas and Crude2x88160
HarthaNatural Gas and Crude4x180300
Out of Service for Unscheduled MaintanenceTotal:1,3222,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations Reporting Peak for 06 MAY 2004 / Report Date - 07 MAY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 x 9 24 Baiji Fuel Oil 6 x 100 500 Daura Fuel Oil 4 0 180 South Baghdad Fuel Oil 6 x x x 85 200 Mussaibe Crude and Fuel Oil 4 x x 415 860 Nassirya Crude 4 x x x 445 600 Najebia Natural Gas and Crude 2 x 88 160 Hartha Natural Gas and Crude 4 x 180 300 Out of Service for Unscheduled Maintanence Total: 1322 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Reporting Peak for 06 MAY 2004 / Report Date - 07 MAY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 2 170 125 Gas Oil Musil Dam Main 4 600 M. Baiji 8 2 40 Gas Oil Musil Dam reg 4 60 Quds 2 1 70 160 Gas Oil Musil Pumping 2 0 Mosil 12 7 115 150 Haditha Dam 6 160 Dibis 3 2 50 30 Samarra 3 55 Old Mulla 12 7 95 128 Himrin 2 21 New Mulla 6 5 140 173 Hindia 4 5 Taji 7 55 Kufa 4 0 M. Taji 2 18 Total 0 896 Daura 4 30 System Generation MWh Hilla 4 4 75 64 Syrian Line Generation MWh Najaf 3 3 110 129 Turkey Line Generation MWh Khor 4 3 146 80 Natural Gas Total Generation 79680 MWh Shuaiba 2 1 15 20 Natural Gas System Peak Load 3162 MW M. Shuaiba 2 Natural Gas Syria Peak Load 60 MW Petro 4 0 Natural Gas Turkey Peak Load 82 MW M. Dibis 4 3 9 24 Natural Gas Fixed Gen Peak Load 266 MW Mossil East 5 3 18 0 Gas Oil Total Peak Load 3570 MW Hmam/Zafranya 7 1 76 Gas Oil Baghdad Load 975 MW Diesel Gas Oil Total 1129 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Reporting Peak for 06 MAY 2004 / Report Date - 07 MAY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 975 Duhok 82 Naynawa 320 Tamim 129 Salah Aldeen 210 Anbar 185 Dyala 85 Babil 116 Kirbala 97 Najaf 90 Kadsya 50 Wasit 95 Muthana 55 Nasirya 125 Misan 70 Basra 270