# A-Steam Power Stations
REPORT DATE - 08 FEBRUARY 2004
A - Steam Power Stations
Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 2 8 8 16 24 #2 boiler leakage; #3 prog maint Baiji Fuel Oil 6 3 90 80 85 255 500 #2 prog maint; #5 forced outage; #6 insulation test Daura Fuel Oil 4 1 65 65 180 #4 rotor repair; #5 & #6 rehab South Baghdad Fuel Oil 6 2 30 30 60 200 #1 H.O. leakage; #2 air heater defect; #5 synch at 2120. stopped at 2210 A/H #6 boiler leakeage Mussaibe Crude and Fuel Oil 4 3 100 200 180 480 860 #1 limited to E.H. G. governor; #4 prog maint Nassirya Crude 4 4 130 150 160 160 600 600 Najebia Natural Gas and Crude 2 1 85 85 160 #4 stopped at 837 boiler leakeage Hartha Natural Gas and Crude 4 1 110 110 300 #4 prog maint Out of Service for Unscheduled Maintanence Total: 1671 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance
# B- Gas_C-Power Stations
Report Date - 08 FEBRUARY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 120 125 Gas Oil #2 lub oil leak from bearing Musil Dam Main 4 4 570 600 Quds 2 1 125 160 Gas Oil #2 FPL - 36 trucks Musil Dam reg 4 4 38 60 1000 Mosil 12 9 148 150 18 #1 rotor defec; #3 bleed valve; #9 rotor defect Musil Pumping 2 1 110 0 Dibis 3 1 28 30 30 #4 & #5 rehab Haditha Dam 6 2 125 160 250 Old Mulla 12 7 102 128 470 #1 acc gear; #2 servo; #5 prog main; #10 prog main; #12 needs rehab Samarra 3 2 42 55 420 New Mulla 6 3 105 173 2.8 #1 prog main; #4 servo; #6 generator defect Himrin 2 2 36 21 130 Taji 7 3 42 55 18 #1 nozzel cleaning; #3 compressor; #4 temp diff; #7 needs rehab Hindia 4 4 5 5 110 M. Taji 2 18 #2 software Kufa 4 3 1 0 30 Daura 4 2 49 30 18 #3 needs rehab Total 927 896 Hilla 4 3 47 64 32 #2 servo System Generation 79478 MWh Najaf 3 2 100 129 31 #2 prog maint Syrian Line Generation 1238 MWh Khor 4 3 120 80 Natural Gas #4 rehab Turkey Line Generation 1970 MWh Shuaiba 2 2 3 20 Natural Gas #2 s/b Total Generation 88113 MWh M. Shuaiba 2 Natural Gas split with refinery System Peak Load 3555 MW Petro 4 0 Natural Gas #2 stopped at 1843 Syria Peak Load 60 MW M. Dibis 4 3 9 24 Natural Gas Turkey Peak Load 85 MW Mossil East 5 3 16 0 Gas Oil Fixed Gen Peak Load 266 MW Hmam/Zafranya 7 2 3 Gas Oil Total Peak Load 3966 MW Diesel 40 Gas Oil Baghdad Load 1355 MW Total 1057 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
Report Date - 08 FEBRUARY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Power transferred from North to Middle 820 MW.
Power transferred from South to Middle 220 MW.
Baghdad 1355 29932 1247
Duhok 85 1930 80
Naynawa 288 6931 289
Tamim 136 3428 143
Salah Aldeen 185 4481 187
Anbar 185 4226 176
Dyala 85 1860 78
Babil 85 2468 103
Kirbala 85 1978 82
Najaf 100 2520 105
Kadsya 65 1405 59
Wasit 80 2200 92
Muthana 59 1313 55
Nasirya 120 2761 115
Misan 61 1481 62
Basra 315 7375 307
الرئيسية / الخدمات الأساسية / ESS-923c25ab
الخدمات الأساسية
System Status Feb 08
- التاريخ
- 8 شباط 2004
- الفئة
- الخدمات الأساسية
- النص متوفر
- الإنكليزية
- عدد الملفات
- 1
معاينة الجدول
الورقة «A-Steam Power Stations»: 16 صفاً × 13 عموداً
| REPORT DATE - 08 FEBRUARY 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type Fuel | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load MW | Remarks | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | |||||||
| Dibis | Natural Gas | 4 | 2 | 8 | 8 | 16 | 24 | #2 boiler leakage; #3 prog maint | ||||
| Baiji | Fuel Oil | 6 | 3 | 90 | 80 | 85 | 255 | 500 | #2 prog maint; #5 forced outage; #6 insulation test | |||
| Daura | Fuel Oil | 4 | 1 | 65 | 65 | 180 | #4 rotor repair; #5 & #6 rehab | |||||
| South Baghdad | Fuel Oil | 6 | 2 | 30 | 30 | 60 | 200 | #1 H.O. leakage; #2 air heater defect; #5 synch at 2120. stopped at 2210 A/H #6 boiler leakeage | ||||
| Mussaibe | Crude and Fuel Oil | 4 | 3 | 100 | 200 | 180 | 480 | 860 | #1 limited to E.H. G. governor; #4 prog maint | |||
| Nassirya | Crude | 4 | 4 | 130 | 150 | 160 | 160 | 600 | 600 | |||
| Najebia | Natural Gas and Crude | 2 | 1 | 85 | 85 | 160 | #4 stopped at 837 boiler leakeage | |||||
| Hartha | Natural Gas and Crude | 4 | 1 | 110 | 110 | 300 | #4 prog maint | |||||
| Out of Service for Unscheduled Maintanence | Total: | 1,671 | 2,824 | |||||||||
| Out of Service for Program Maintanence/Rehab | ||||||||||||
| No activity | ||||||||||||
| Not Performing at Peak Performance |
الورقة «B- Gas_C-Power Stations»: 26 صفاً × 13 عموداً
| Report Date - 08 FEBRUARY 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 120 | 125 | Gas Oil | #2 lub oil leak from bearing | Musil Dam Main | 4 | 4 | 570 | 600 | |
| Quds | 2 | 1 | 125 | 160 | Gas Oil | #2 FPL - 36 trucks | Musil Dam reg | 4 | 4 | 38 | 60 | 1,000 |
| Mosil | 12 | 9 | 148 | 150 | 18 | #1 rotor defec; #3 bleed valve; #9 rotor defect | Musil Pumping | 2 | 1 | 110 | 0 | |
| Dibis | 3 | 1 | 28 | 30 | 30 | #4 & #5 rehab | Haditha Dam | 6 | 2 | 125 | 160 | 250 |
| Old Mulla | 12 | 7 | 102 | 128 | 470 | #1 acc gear; #2 servo; #5 prog main; #10 prog main; #12 needs rehab | Samarra | 3 | 2 | 42 | 55 | 420 |
| New Mulla | 6 | 3 | 105 | 173 | 2.80 | #1 prog main; #4 servo; #6 generator defect | Himrin | 2 | 2 | 36 | 21 | 130 |
| Taji | 7 | 3 | 42 | 55 | 18 | #1 nozzel cleaning; #3 compressor; #4 temp diff; #7 needs rehab | Hindia | 4 | 4 | 5 | 5 | 110 |
| M. Taji | 2 | 18 | #2 software | Kufa | 4 | 3 | 1 | 0 | 30 | |||
| Daura | 4 | 2 | 49 | 30 | 18 | #3 needs rehab | Total | 927 | 896 | |||
| Hilla | 4 | 3 | 47 | 64 | 32 | #2 servo | System Generation | 79,478 | MWh | |||
| Najaf | 3 | 2 | 100 | 129 | 31 | #2 prog maint | Syrian Line Generation | 1,238 | MWh | |||
| Khor | 4 | 3 | 120 | 80 | Natural Gas | #4 rehab | Turkey Line Generation | 1,970 | MWh | |||
| Shuaiba | 2 | 2 | 3 | 20 | Natural Gas | #2 s/b | Total Generation | 88,113 | MWh | |||
| M. Shuaiba | 2 | Natural Gas | split with refinery | System Peak Load | 3,555 | MW | ||||||
| Petro | 4 | 0 | Natural Gas | #2 stopped at 1843 | Syria Peak Load | 60 | MW | |||||
| M. Dibis | 4 | 3 | 9 | 24 | Natural Gas | Turkey Peak Load | 85 | MW | ||||
| Mossil East | 5 | 3 | 16 | 0 | Gas Oil | Fixed Gen Peak Load | 266 | MW | ||||
| Hmam/Zafranya | 7 | 2 | 3 | Gas Oil | Total Peak Load | 3,966 | MW | |||||
| Diesel | 40 | Gas Oil | Baghdad Load | 1,355 | MW | |||||||
| Total | 1,057 | 1,186 | ||||||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
الورقة «Peak Loads»: 24 صفاً × 4 أعمدة · المعاينة لأول 21 صفاً؛ الملف الكامل من زر الأصل
| Report Date - 08 FEBRUARY 2004 | |||
|---|---|---|---|
| GOVERNORATE | Peak Load MW | MWH | Average Load MW |
| Power transferred from North to Middle 820 MW. | |||
| Power transferred from South to Middle 220 MW. | |||
| Baghdad | 1,355 | 29,932 | 1,247 |
| Duhok | 85 | 1,930 | 80 |
| Naynawa | 288 | 6,931 | 289 |
| Tamim | 136 | 3,428 | 143 |
| Salah Aldeen | 185 | 4,481 | 187 |
| Anbar | 185 | 4,226 | 176 |
| Dyala | 85 | 1,860 | 78 |
| Babil | 85 | 2,468 | 103 |
| Kirbala | 85 | 1,978 | 82 |
| Najaf | 100 | 2,520 | 105 |
| Kadsya | 65 | 1,405 | 59 |
| Wasit | 80 | 2,200 | 92 |
| Muthana | 59 | 1,313 | 55 |
| Nasirya | 120 | 2,761 | 115 |
| Misan | 61 | 1,481 | 62 |
| Basra | 315 | 7,375 | 307 |