# A-Steam Power Stations
REPORT DATE -28 October 2003 A - Steam Power Stations Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 2 7 0 0 7 14 24 No. 2 Boiler Leakage. No. 3 Stopped due to carbon brushes.
Baiji Fuel Oil 6 3 - 95 85 0 0 85 275 500 No. 2 Boiler Leakage. No. 4 Working on Drum and Boiler Leakage. No. 5 Rehab.
Dura Fuel Oil 4 1 75 0 0 0 75 180 No.5 & 6 Rehabilitation Program. No. 4 Programmed Maintenance.
South Baghdad Fuel Oil 6 3 0 0 0 35 40 15 90 200 No. 1 change baskets. No. 3 Air Heaters.
Mussaibe Crude and Fuel Oil 4 3 210 0 110 215 535 860 No. 2 working on control system. No. 3 Synchronized at 7:37 Nassirya Crude 4 4 150 160 160 85 555 600 No. 4 limited vacuum.
Najebia Natural Gas and Crude 2 1 85 0 85 160 No. 5 turbine bearing.
Hartha Natural Gas and Crude 4 1 150 0 150 300 No. 4 programed maintenance from 24 October.
Total: 1779 2824
# B- Gas_C-Power Stations
Report Date- 28 October 2003 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 115 125 Gas Oil No. 2 Change Cooling Board and Balance. Musil Dam Main 4 2 300 600 Quds 2 2 110 160 Gas Oil 44 Trucks. Musil Dam reg 4 3 30 60 400 Mosil 12 2 22 150 Gas Oil No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. No. 5, 6, 9, 10, 11, 12 S/B NGPL. Musil Pumping 2 0 0 0 Dibis 3 1 11 60 28 No. 6 repair turbine rotor. No. 5 problem turbine rotor. Haditha Dam 6 2 95 160 300 Old Mulla 12 6 80 128 460 No. 1 excitation, No. 11 programmed mnt. No. 7 primary protec. No. 12 rehab. No. 2 clutch. Samarra 3 2 37 55 370 New Mulla 6 5 160 173 35 No. 6 Generator Defective Himrin 2 1 23 21 100 Taji 7 4 64 55 18 No. 1 Programmed Maintenance. No. 5 Diesel. No.7 Rehabilitation. Hindia 4 4 5 5 130 M. Taji 2 0 0 20 0 NGPL Kufa 4 1 1 1 30 Dura 4 2 35 30 17 No.1 Control. No.3 Rehabilitation. Total 491 896 Hilla 4 4 64 64 22 System Generation 77462 MWh Najaf 3 3 130 129 21 Syrian Line Generation 1375 MWh Khor 4 3 110 80 Natural Gas No. 4 Rehabilitation. Turkey Line Generation 1647 MWh Shuaiba 2 1 5 20 Natural Gas One unit S/B Total Generation 77484 MWh Petro 4 1 10 0 Natural Gas System Peak Load 3573 MW M. Dibis 4 0 0 24 Natural Gas Turkey Peak Load 60 MW Mossil East 5 0 0 15 Gas Oil Syria Peak Load 95 MW Hmam 2 0 0 Gas Oil Fixed Gen Peak Load 77 MW Dieel 0 Total Peak Load 3805 MW Total 916 1233 Baghdad Load 1170 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
GOVERNORATE Peak Load MW MWH Average Load MW 28 October, 2003 Baghdad 1170 24085 1003.5417 Power transferred from North to Middle 650 MW Duhok 95 1668 69.5 Naynawa 280 6824 284.3333 Power transferred from South to Middle 250 MW Tamim 135 3306 137.75 Salah Aldeen 210 4556 189.8333 Anbar 190 3835 159.7917 Dyala 80 1740 72.5 Babil 125 2468 102.8333 Kirbala 75 1710 71.25 Najaf 120 2529 105.375 Kadsya 65 1394 58.0833 Wasit 85 2062 85.9167 Muthana 75 1568 65.3333 Nasirya 125 2806 116.9167 Misan 70 1627 67.7917 Basra 310 6990 291.25 3210
الرئيسية / الخدمات الأساسية / ESS-73df74d1
الخدمات الأساسية
power system29oct03
- التاريخ
- 28 تشرين الأول 2003
- الفئة
- الخدمات الأساسية
- النص متوفر
- الإنكليزية
- عدد الملفات
- 1
معاينة الجدول
الورقة «A-Steam Power Stations»: 13 صفاً × 13 عموداً
| REPORT DATE -28 October 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load | Remarks | |||||
| Fuel | 1 | 2 | 3 | 4 | 5 | 6 | MW | |||||
| Dibis | Natural Gas | 4 | 2 | 7 | 0 | 0 | 7 | 14 | 24 | No. 2 Boiler Leakage. No. 3 Stopped due to carbon brushes. | ||
| Baiji | Fuel Oil | 6 | 3 | - | 95 | 85 | 0 | 0 | 85 | 275 | 500 | No. 2 Boiler Leakage. No. 4 Working on Drum and Boiler Leakage. No. 5 Rehab. |
| Dura | Fuel Oil | 4 | 1 | 75 | 0 | 0 | 0 | 75 | 180 | No.5 & 6 Rehabilitation Program. No. 4 Programmed Maintenance. | ||
| South Baghdad | Fuel Oil | 6 | 3 | 0 | 0 | 0 | 35 | 40 | 15 | 90 | 200 | No. 1 change baskets. No. 3 Air Heaters. |
| Mussaibe | Crude and Fuel Oil | 4 | 3 | 210 | 0 | 110 | 215 | 535 | 860 | No. 2 working on control system. No. 3 Synchronized at 7:37 | ||
| Nassirya | Crude | 4 | 4 | 150 | 160 | 160 | 85 | 555 | 600 | No. 4 limited vacuum. | ||
| Najebia | Natural Gas and Crude | 2 | 1 | 85 | 0 | 85 | 160 | No. 5 turbine bearing. | ||||
| Hartha | Natural Gas and Crude | 4 | 1 | 150 | 0 | 150 | 300 | No. 4 programed maintenance from 24 October. | ||||
| Total: | 1,779 | 2,824 |
الورقة «B- Gas_C-Power Stations»: 25 صفاً × 13 عموداً
| Report Date- 28 October 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 115 | 125 | Gas Oil | No. 2 Change Cooling Board and Balance. | Musil Dam Main | 4 | 2 | 300 | 600 | |
| Quds | 2 | 2 | 110 | 160 | Gas Oil | 44 Trucks. | Musil Dam reg | 4 | 3 | 30 | 60 | 400 |
| Mosil | 12 | 2 | 22 | 150 | Gas Oil | No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. No. 5, 6, 9, 10, 11, 12 S/B NGPL. | Musil Pumping | 2 | 0 | 0 | 0 | |
| Dibis | 3 | 1 | 11 | 60 | 28 | No. 6 repair turbine rotor. No. 5 problem turbine rotor. | Haditha Dam | 6 | 2 | 95 | 160 | 300 |
| Old Mulla | 12 | 6 | 80 | 128 | 460 | No. 1 excitation, No. 11 programmed mnt. No. 7 primary protec. No. 12 rehab. No. 2 clutch. | Samarra | 3 | 2 | 37 | 55 | 370 |
| New Mulla | 6 | 5 | 160 | 173 | 35 | No. 6 Generator Defective | Himrin | 2 | 1 | 23 | 21 | 100 |
| Taji | 7 | 4 | 64 | 55 | 18 | No. 1 Programmed Maintenance. No. 5 Diesel. No.7 Rehabilitation. | Hindia | 4 | 4 | 5 | 5 | 130 |
| M. Taji | 2 | 0 | 0 | 20 | 0 | NGPL | Kufa | 4 | 1 | 1 | 1 | 30 |
| Dura | 4 | 2 | 35 | 30 | 17 | No.1 Control. No.3 Rehabilitation. | Total | 491 | 896 | |||
| Hilla | 4 | 4 | 64 | 64 | 22 | System Generation | 77,462 | MWh | ||||
| Najaf | 3 | 3 | 130 | 129 | 21 | Syrian Line Generation | 1,375 | MWh | ||||
| Khor | 4 | 3 | 110 | 80 | Natural Gas | No. 4 Rehabilitation. | Turkey Line Generation | 1,647 | MWh | |||
| Shuaiba | 2 | 1 | 5 | 20 | Natural Gas | One unit S/B | Total Generation | 77,484 | MWh | |||
| Petro | 4 | 1 | 10 | 0 | Natural Gas | System Peak Load | 3,573 | MW | ||||
| M. Dibis | 4 | 0 | 0 | 24 | Natural Gas | Turkey Peak Load | 60 | MW | ||||
| Mossil East | 5 | 0 | 0 | 15 | Gas Oil | Syria Peak Load | 95 | MW | ||||
| Hmam | 2 | 0 | 0 | Gas Oil | Fixed Gen Peak Load | 77 | MW | |||||
| Dieel | 0 | Total Peak Load | 3,805 | MW | ||||||||
| Total | 916 | 1,233 | Baghdad Load | 1,170 | MW | |||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
الورقة «Peak Loads»: 21 صفاً × 5 أعمدة · المعاينة لأول 19 صفاً؛ الملف الكامل من زر الأصل
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | 28 October, 2003 |
|---|---|---|---|---|
| Baghdad | 1,170 | 24,085 | 1,003.54 | Power transferred from North to Middle 650 MW |
| Duhok | 95 | 1,668 | 69.50 | |
| Naynawa | 280 | 6,824 | 284.33 | Power transferred from South to Middle 250 MW |
| Tamim | 135 | 3,306 | 137.75 | |
| Salah Aldeen | 210 | 4,556 | 189.83 | |
| Anbar | 190 | 3,835 | 159.79 | |
| Dyala | 80 | 1,740 | 72.50 | |
| Babil | 125 | 2,468 | 102.83 | |
| Kirbala | 75 | 1,710 | 71.25 | |
| Najaf | 120 | 2,529 | 105.38 | |
| Kadsya | 65 | 1,394 | 58.08 | |
| Wasit | 85 | 2,062 | 85.92 | |
| Muthana | 75 | 1,568 | 65.33 | |
| Nasirya | 125 | 2,806 | 116.92 | |
| Misan | 70 | 1,627 | 67.79 | |
| Basra | 310 | 6,990 | 291.25 | |
| 3,210 |