# A-Steam Power Stations
REPORT DATE -14 NOVEMBER 2003
A - Steam Power Stations
Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 2 0 0 8 8 16 24 No. 2 Boiler Leakage. No. 1 stopped FWP.
Baiji Fuel Oil 6 4 105 90 0 80 0 85 360 500 No. 5 rehab. No. 3 boiler leakage.
Dura Fuel Oil 4 1 75 0 0 0 75 180 No. 4: Programmed Maintenance10 OCT to 25 NOV. Nos. 5 & 6: Rehabilitation.
South Baghdad Fuel Oil 6 3 40 0 20 35 0 0 95 200 No.2 Boiler Leakage. No. 6 programmed mnt 11 NOV to 26 DEC. No. 5 tripped boiler leakage.
Mussaibe Crude and Fuel Oil 4 2 210 0 0 210 420 860 No. 2 program mnt 20 OCT to 12 NOV. No. 3 program mnt 5 NOV to 20 DEC.
Nassirya Crude 4 3 150 150 0 100 400 600 No. 4 limited due to vacuum. No. 3 programmed mnt 11 NOV to 11 DEC.
Najebia Natural Gas and Crude 2 1 0 90 90 160 No. 4 programmed mnt 6 NOV to 21 DEC.
Hartha Natural Gas and Crude 4 1 150 0 150 300 No. 4 Programmed Maintenance from 23 OCT to 23 DEC.
Total: 1606 2824
# B- Gas_C-Power Stations
Report Date- 14 NOVEMBER 2003 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 95 125 Gas Oil No. 2 s/b. Musil Dam Main 4 2 210 600 Quds 2 2 150 160 Gas Oil 37 trucks. Musil Dam reg 4 3 35 60 450 Mosil 12 9 90 150 15 No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. Musil Pumping 2 0 0 0 Dibis 3 0 0 60 31 No. 5 problem turbine rotor. No. 6: Programmed Maintenance. No. 4 rotor defect. Haditha Dam 6 2 75 160 300 Old Mulla 12 6 75 128 29 No. 1 gas control. No. 2 gen protec. No.3 servo. No. 5 Programmed Mnt. No. 11 isolation. No. 12 rehab. Samarra 3 3 45 55 455 New Mulla 6 4 150 173 21 No. 6 Generator Defective. No. 3 programmed mnt. Himrin 2 1 23 21 130 Taji 7 5 75 55 13 No. 5 Diesel. No.7 Rehabilitation. Hindia 4 4 5 5 120 M. Taji 2 0 0 20 0 NGPL Kufa 4 2 1 1 60 Dura 4 0 0 30 14 No.1 Control. No.3 Rehabilitation. No. 2 NGPL. No. 4 NGPL. Total 394 896 Hilla 4 4 70 64 22 System Generation 70261 MWh Najaf 3 3 95 129 24 Syrian Line Generation 1417 MWh Khor 4 2 84 80 Natural Gas No. 4: Rehabilitation. No. 2 tripped on 13 NOV o/s. Turkey Line Generation 2078 MWh Shuaiba 2 1 5 20 Natural Gas No. 1 Programmed Maintenance. Total Generation 73756 MWh Petro 4 1 10 0 Natural Gas System Peak Load 3519 MW M. Dibis 4 0 0 24 Natural Gas Syria Peak Load 60 MW Mossil East 5 0 0 15 Gas Oil Turkey Peak Load 88 MW Hmam 2 0 0 Gas Oil Fixed Gen Peak Load 77 MW Total Peak Load 3744 MW Total 899 1233 Baghdad Load 975 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
GOVERNORATE Peak Load MW MWH Average Load MW 14 NOVEMBER, 2003 Baghdad 1100 23437 976.5417 Power transferred from North to Middle 550 MW Duhok 80 1980 82.5 Naynawa 365 8010 333.75 Power transferred from South to Middle 180 MW Tamim 165 3585 149.375 Salah Aldeen 225 4757 198.2083 Anbar 165 4069 169.5417 Dyala 75 1983 82.625 Babil 85 2156 89.8333 Kirbala 75 1667 69.4583 Najaf 115 2355 98.125 Kadsya 75 1388 57.8333 Wasit 85 1869 77.875 Muthana 70 1508 62.8333 Nasirya 125 2739 114.125 Misan 70 1442 60.0833 Basra 310 4897 204.0417 3185
Home / Essential Services / ESS-fbb6adff
Essential Services
power system15nov03
- Date
- 14 November 2003
- Category
- Essential Services
- Text available
- English
- Files
- 1
Spreadsheet preview
Sheet “A-Steam Power Stations”: 13 rows × 13 columns
| REPORT DATE -14 NOVEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load | Remarks | |||||
| Fuel | 1 | 2 | 3 | 4 | 5 | 6 | MW | |||||
| Dibis | Natural Gas | 4 | 2 | 0 | 0 | 8 | 8 | 16 | 24 | No. 2 Boiler Leakage. No. 1 stopped FWP. | ||
| Baiji | Fuel Oil | 6 | 4 | 105 | 90 | 0 | 80 | 0 | 85 | 360 | 500 | No. 5 rehab. No. 3 boiler leakage. |
| Dura | Fuel Oil | 4 | 1 | 75 | 0 | 0 | 0 | 75 | 180 | No. 4: Programmed Maintenance10 OCT to 25 NOV. Nos. 5 & 6: Rehabilitation. | ||
| South Baghdad | Fuel Oil | 6 | 3 | 40 | 0 | 20 | 35 | 0 | 0 | 95 | 200 | No.2 Boiler Leakage. No. 6 programmed mnt 11 NOV to 26 DEC. No. 5 tripped boiler leakage. |
| Mussaibe | Crude and Fuel Oil | 4 | 2 | 210 | 0 | 0 | 210 | 420 | 860 | No. 2 program mnt 20 OCT to 12 NOV. No. 3 program mnt 5 NOV to 20 DEC. | ||
| Nassirya | Crude | 4 | 3 | 150 | 150 | 0 | 100 | 400 | 600 | No. 4 limited due to vacuum. No. 3 programmed mnt 11 NOV to 11 DEC. | ||
| Najebia | Natural Gas and Crude | 2 | 1 | 0 | 90 | 90 | 160 | No. 4 programmed mnt 6 NOV to 21 DEC. | ||||
| Hartha | Natural Gas and Crude | 4 | 1 | 150 | 0 | 150 | 300 | No. 4 Programmed Maintenance from 23 OCT to 23 DEC. | ||||
| Total: | 1,606 | 2,824 |
Sheet “B- Gas_C-Power Stations”: 25 rows × 13 columns
| Report Date- 14 NOVEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 95 | 125 | Gas Oil | No. 2 s/b. | Musil Dam Main | 4 | 2 | 210 | 600 | |
| Quds | 2 | 2 | 150 | 160 | Gas Oil | 37 trucks. | Musil Dam reg | 4 | 3 | 35 | 60 | 450 |
| Mosil | 12 | 9 | 90 | 150 | 15 | No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. | Musil Pumping | 2 | 0 | 0 | 0 | |
| Dibis | 3 | 0 | 0 | 60 | 31 | No. 5 problem turbine rotor. No. 6: Programmed Maintenance. No. 4 rotor defect. | Haditha Dam | 6 | 2 | 75 | 160 | 300 |
| Old Mulla | 12 | 6 | 75 | 128 | 29 | No. 1 gas control. No. 2 gen protec. No.3 servo. No. 5 Programmed Mnt. No. 11 isolation. No. 12 rehab. | Samarra | 3 | 3 | 45 | 55 | 455 |
| New Mulla | 6 | 4 | 150 | 173 | 21 | No. 6 Generator Defective. No. 3 programmed mnt. | Himrin | 2 | 1 | 23 | 21 | 130 |
| Taji | 7 | 5 | 75 | 55 | 13 | No. 5 Diesel. No.7 Rehabilitation. | Hindia | 4 | 4 | 5 | 5 | 120 |
| M. Taji | 2 | 0 | 0 | 20 | 0 | NGPL | Kufa | 4 | 2 | 1 | 1 | 60 |
| Dura | 4 | 0 | 0 | 30 | 14 | No.1 Control. No.3 Rehabilitation. No. 2 NGPL. No. 4 NGPL. | Total | 394 | 896 | |||
| Hilla | 4 | 4 | 70 | 64 | 22 | System Generation | 70,261 | MWh | ||||
| Najaf | 3 | 3 | 95 | 129 | 24 | Syrian Line Generation | 1,417 | MWh | ||||
| Khor | 4 | 2 | 84 | 80 | Natural Gas | No. 4: Rehabilitation. No. 2 tripped on 13 NOV o/s. | Turkey Line Generation | 2,078 | MWh | |||
| Shuaiba | 2 | 1 | 5 | 20 | Natural Gas | No. 1 Programmed Maintenance. | Total Generation | 73,756 | MWh | |||
| Petro | 4 | 1 | 10 | 0 | Natural Gas | System Peak Load | 3,519 | MW | ||||
| M. Dibis | 4 | 0 | 0 | 24 | Natural Gas | Syria Peak Load | 60 | MW | ||||
| Mossil East | 5 | 0 | 0 | 15 | Gas Oil | Turkey Peak Load | 88 | MW | ||||
| Hmam | 2 | 0 | 0 | Gas Oil | Fixed Gen Peak Load | 77 | MW | |||||
| Total Peak Load | 3,744 | MW | ||||||||||
| Total | 899 | 1,233 | Baghdad Load | 975 | MW | |||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
Sheet “Peak Loads”: 21 rows × 5 columns · preview of the first 19 rows; full file from the original button
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | 14 NOVEMBER, 2003 |
|---|---|---|---|---|
| Baghdad | 1,100 | 23,437 | 976.54 | Power transferred from North to Middle 550 MW |
| Duhok | 80 | 1,980 | 82.50 | |
| Naynawa | 365 | 8,010 | 333.75 | Power transferred from South to Middle 180 MW |
| Tamim | 165 | 3,585 | 149.38 | |
| Salah Aldeen | 225 | 4,757 | 198.21 | |
| Anbar | 165 | 4,069 | 169.54 | |
| Dyala | 75 | 1,983 | 82.62 | |
| Babil | 85 | 2,156 | 89.83 | |
| Kirbala | 75 | 1,667 | 69.46 | |
| Najaf | 115 | 2,355 | 98.12 | |
| Kadsya | 75 | 1,388 | 57.83 | |
| Wasit | 85 | 1,869 | 77.88 | |
| Muthana | 70 | 1,508 | 62.83 | |
| Nasirya | 125 | 2,739 | 114.12 | |
| Misan | 70 | 1,442 | 60.08 | |
| Basra | 310 | 4,897 | 204.04 | |
| 3,185 |