# A-Steam Power Stations
REPORT DATE - 8 January 2004 A - Steam Power Stations Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 1 0 0 7 7 24 #1 prog maint.10 DEC to 25 JAN. #2 Stopped 1/7, unstable water level, #3 FWF.
Baiji Fuel Oil 6 3 95 0 65 95 0 0 255 500 #2 lack of HCL. #6 prog maint. 5 DEC to 19 JAN.
Daura Fuel Oil 4 1 75 0 0 0 75 180 No. 4 Repair of bearing, Nos. 5 & 6: Rehab.
South Baghdad Fuel Oil 6 2 0 0 20 30 0 0 50 200 #1 Boiler Leak, #2 A/H, #6 Thrust bearing, #5 prog maint Mussaibe Crude and Fuel Oil 4 3 210 0 100 210 520 860 #2 Inspection/Seal treatment Nassirya Crude 4 3 130 140 145 0 415 600 #4 prog maint. 28 DEC to 28 JAN.
Najebia Natural Gas and Crude 2 2 40 90 130 160 #4 only one boiler in operation-degraded Hartha Natural Gas and Crude 4 1 140 0 140 300 #4 prog maint.
Total: 1592 2824
# B- Gas_C-Power Stations
Report Date- 8 January 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 125 125 Gas Oil No. 2 lubricating oil leak Musil Dam Main 4 3 300 600 Qudis 2 1 115 160 Gas Oil 39 truck #2 C/B problem Musil Dam reg 4 3 35 60 450 Mosil 12 8 128 150 27 #1 Rotor Defect. #2 servo ACC. #3 Prog Maint. #9 rotor defect. Musil Pumping 2 - - - Dibis 3 1 30 30 24 #4 and 5 rehab.. Haditha Dam 6 2 140 160 300 Old Mulla 12 7 98 128 380 #1 ACC gear, #2 servo, #5 Prog maint, #7 progm maint, #12 rehab. Samarra 3 2 33 55 400 New Mulla 6 3 73 73 27 #4, 5 prog maint, #6 Generator defect Himrin 2 1 22 21 90 Taji 7 4 56 56 15 #3 Compressor, #4 Turbine, #7 Rehab. Hindia 4 3 5 5 M. Taji 2 1 7 18 Natural Gas #2 software. Kufa 4 - - 0 Daura 4 3 75 30 16 #3 Rehab Total 535 896 Hilla 4 4 72 64 27 System Generation 69968 MWh Najaf 3 2 100 129 25 #2 prog maint Syrian Line Generation 1452 MWh Khor 4 3 110 80 Natural Gas #4 Rehab Turkey Line Generation 1894 MWh Shuaiba 2 2 16 20 Natural Gas Total Generation 73314 MWh Petro 4 1 10 0 Natural Gas System Peak Load 3234 MW M. Dibis 4 4 12 24 Natural Gas Syria Peak Load 60 MW Mossil East 5 1 5 0 Gas Oil Turkey Peak Load 80 MW Hmam/Zafranya 7 2 3 Gas Oil Fixed Gen Peak Load 77 MW Diesel 9 Gas Oil Total Peak Load 3451 MW Total 1044 1087 Baghdad Load 1250 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
GOVERNORATE Peak Load MW MWH Average Load MW 8 January, 2004 Baghdad 1250 26509 1104.5417 Power transferred from North to Middle 460 MW.
Duhok 80 1821 75.875
Naynawa 330 7026 292.75 Power transferred from South to Middle 140 MW.
Tamim 135 2788 116.1667
Salah Aldeen 165 4403 183.4583 Anbar 145 3736 155.6667 Dyala 75 1689 70.375 Babil 95 1917 80 Kirbala 55 1375 57.2917 Najaf 80 2056 85.6667 Kadsya 55 1212 50.5 Wasit 85 1390 57.9167 Muthana 50 1176 49 Nasirya 120 2723 113.4583 Misan 65 1306 54.4167 Basra 320 6612 275.5 3105
Home / Essential Services / ESS-7350ea91
Essential Services
Power System 8 Jan
- Date
- 8 January 2004
- Category
- Essential Services
- Text available
- English
- Files
- 1
Spreadsheet preview
Sheet “A-Steam Power Stations”: 13 rows × 13 columns
| REPORT DATE - 8 January 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load | Remarks | |||||
| Fuel | 1 | 2 | 3 | 4 | 5 | 6 | MW | |||||
| Dibis | Natural Gas | 4 | 1 | 0 | 0 | 7 | 7 | 24 | #1 prog maint.10 DEC to 25 JAN. #2 Stopped 1/7, unstable water level, #3 FWF. | |||
| Baiji | Fuel Oil | 6 | 3 | 95 | 0 | 65 | 95 | 0 | 0 | 255 | 500 | #2 lack of HCL. #6 prog maint. 5 DEC to 19 JAN. |
| Daura | Fuel Oil | 4 | 1 | 75 | 0 | 0 | 0 | 75 | 180 | No. 4 Repair of bearing, Nos. 5 & 6: Rehab. | ||
| South Baghdad | Fuel Oil | 6 | 2 | 0 | 0 | 20 | 30 | 0 | 0 | 50 | 200 | #1 Boiler Leak, #2 A/H, #6 Thrust bearing, #5 prog maint |
| Mussaibe | Crude and Fuel Oil | 4 | 3 | 210 | 0 | 100 | 210 | 520 | 860 | #2 Inspection/Seal treatment | ||
| Nassirya | Crude | 4 | 3 | 130 | 140 | 145 | 0 | 415 | 600 | #4 prog maint. 28 DEC to 28 JAN. | ||
| Najebia | Natural Gas and Crude | 2 | 2 | 40 | 90 | 130 | 160 | #4 only one boiler in operation-degraded | ||||
| Hartha | Natural Gas and Crude | 4 | 1 | 140 | 0 | 140 | 300 | #4 prog maint. | ||||
| Total: | 1,592 | 2,824 |
Sheet “B- Gas_C-Power Stations”: 25 rows × 13 columns
| Report Date- 8 January 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 125 | 125 | Gas Oil | No. 2 lubricating oil leak | Musil Dam Main | 4 | 3 | 300 | 600 | |
| Qudis | 2 | 1 | 115 | 160 | Gas Oil | 39 truck #2 C/B problem | Musil Dam reg | 4 | 3 | 35 | 60 | 450 |
| Mosil | 12 | 8 | 128 | 150 | 27 | #1 Rotor Defect. #2 servo ACC. #3 Prog Maint. #9 rotor defect. | Musil Pumping | 2 | - | - | - | |
| Dibis | 3 | 1 | 30 | 30 | 24 | #4 and 5 rehab.. | Haditha Dam | 6 | 2 | 140 | 160 | 300 |
| Old Mulla | 12 | 7 | 98 | 128 | 380 | #1 ACC gear, #2 servo, #5 Prog maint, #7 progm maint, #12 rehab. | Samarra | 3 | 2 | 33 | 55 | 400 |
| New Mulla | 6 | 3 | 73 | 73 | 27 | #4, 5 prog maint, #6 Generator defect | Himrin | 2 | 1 | 22 | 21 | 90 |
| Taji | 7 | 4 | 56 | 56 | 15 | #3 Compressor, #4 Turbine, #7 Rehab. | Hindia | 4 | 3 | 5 | 5 | |
| M. Taji | 2 | 1 | 7 | 18 | Natural Gas | #2 software. | Kufa | 4 | - | - | 0 | |
| Daura | 4 | 3 | 75 | 30 | 16 | #3 Rehab | Total | 535 | 896 | |||
| Hilla | 4 | 4 | 72 | 64 | 27 | System Generation | 69,968 | MWh | ||||
| Najaf | 3 | 2 | 100 | 129 | 25 | #2 prog maint | Syrian Line Generation | 1,452 | MWh | |||
| Khor | 4 | 3 | 110 | 80 | Natural Gas | #4 Rehab | Turkey Line Generation | 1,894 | MWh | |||
| Shuaiba | 2 | 2 | 16 | 20 | Natural Gas | Total Generation | 73,314 | MWh | ||||
| Petro | 4 | 1 | 10 | 0 | Natural Gas | System Peak Load | 3,234 | MW | ||||
| M. Dibis | 4 | 4 | 12 | 24 | Natural Gas | Syria Peak Load | 60 | MW | ||||
| Mossil East | 5 | 1 | 5 | 0 | Gas Oil | Turkey Peak Load | 80 | MW | ||||
| Hmam/Zafranya | 7 | 2 | 3 | Gas Oil | Fixed Gen Peak Load | 77 | MW | |||||
| Diesel | 9 | Gas Oil | Total Peak Load | 3,451 | MW | |||||||
| Total | 1,044 | 1,087 | Baghdad Load | 1,250 | MW | |||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
Sheet “Peak Loads”: 21 rows × 5 columns · preview of the first 19 rows; full file from the original button
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | 8 January, 2004 |
|---|---|---|---|---|
| Baghdad | 1,250 | 26,509 | 1,104.54 | Power transferred from North to Middle 460 MW. |
| Duhok | 80 | 1,821 | 75.88 | |
| Naynawa | 330 | 7,026 | 292.75 | Power transferred from South to Middle 140 MW. |
| Tamim | 135 | 2,788 | 116.17 | |
| Salah Aldeen | 165 | 4,403 | 183.46 | |
| Anbar | 145 | 3,736 | 155.67 | |
| Dyala | 75 | 1,689 | 70.38 | |
| Babil | 95 | 1,917 | 80 | |
| Kirbala | 55 | 1,375 | 57.29 | |
| Najaf | 80 | 2,056 | 85.67 | |
| Kadsya | 55 | 1,212 | 50.50 | |
| Wasit | 85 | 1,390 | 57.92 | |
| Muthana | 50 | 1,176 | 49 | |
| Nasirya | 120 | 2,723 | 113.46 | |
| Misan | 65 | 1,306 | 54.42 | |
| Basra | 320 | 6,612 | 275.50 | |
| 3,105 |