Sheet “A-Steam Power Stations”: 16 rows × 13 columns

REPORT DATE - 03 FEBRUARY 2004
A - Steam Power Stations
Power StationsType FuelNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget Load MWRemarks
123456
DibisNatural Gas42991824
BaijiFuel Oil619090500#3 stopped - tripped by furn press high
DauraFuel Oil417070180
South BaghdadFuel Oil613030200
MussaibeCrude and Fuel Oil44170170170170680860#1 tripped by EHG with (200) MW
NassiryaCrude4315090140380600#3 synchro at 515
NajebiaNatural Gas and Crude229085175160
HarthaNatural Gas and Crude418080300
Out of Service for Unscheduled MaintanenceTotal:1,5232,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations REPORT DATE - 03 FEBRUARY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 2 9 9 18 24 Baiji Fuel Oil 6 1 90 90 500 #3 stopped - tripped by furn press high Daura Fuel Oil 4 1 70 70 180 South Baghdad Fuel Oil 6 1 30 30 200 Mussaibe Crude and Fuel Oil 4 4 170 170 170 170 680 860 #1 tripped by EHG with (200) MW Nassirya Crude 4 3 150 90 140 380 600 #3 synchro at 515 Najebia Natural Gas and Crude 2 2 90 85 175 160 Hartha Natural Gas and Crude 4 1 80 80 300 Out of Service for Unscheduled Maintanence Total: 1523 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Report Date - 03 FEBRUARY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 0 0 125 Gas Oil Musil Dam Main 4 4 580 600 Quds 2 2 230 160 Gas Oil #1 emerg stop due to turb filters cleaning Musil Dam reg 4 4 37 60 Mosil 12 9 142 150 #3 emerg stop due to n. gas pressure low Musil Pumping 2 1 110 0 Dibis 3 1 30 30 Haditha Dam 6 160 Old Mulla 12 7 86 128 #4 tripped by turb vibration Samarra 3 2 44 55 New Mulla 6 3 105 173 Himrin 2 2 34 21 Taji 7 4 69 55 Hindia 4 4 5 5 M. Taji 2 1 8 18 Kufa 4 2 1 0 Daura 4 2 50 30 Total 811 896 Hilla 4 4 68 64 System Generation MWh Najaf 3 2 90 129 Syrian Line Generation MWh Khor 4 3 130 80 Natural Gas Turkey Line Generation MWh Shuaiba 2 2 7 20 Natural Gas Total Generation 87835 MWh M. Shuaiba 2 Natural Gas System Peak Load 3542 MW Petro 4 1 42 0 Natural Gas Syria Peak Load 60 MW M. Dibis 4 0 0 24 Natural Gas Turkey Peak Load 80 MW Mossil East 5 3 18 0 Gas Oil Fixed Gen Peak Load 266 MW Hmam/Zafranya 7 3 45 Gas Oil Total Peak Load 3928 MW Diesel Gas Oil Baghdad Load 1470 MW Total 1120 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Report Date - 03 FEBRUARY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1470 Duhok 80 Naynawa 32 Tamim 125 Salah Aldeen 190 Anbar 180 Dyala 100 Babil 95 Kirbala 90 Najaf 110 Kadsya 65 Wasit 95 Muthana 60 Nasirya 110 Misan 55 Basra 320 3470