# A-Steam Power Stations
Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 1 8 8 24 #2 DLL; #3 gen earth fault; #4 prog maint Baiji Fuel Oil 6 2 140 105 245 500 #1, #3 prog maint; #4 stopped at 0010 under excit; #5 forced outage Daura Fuel Oil 4 0 180 #3, #4 prog maint; #5, #6 rehab South Baghdad Fuel Oil 6 3 30 30 25 85 200 #1, #2, #3 prog maint Mussaibe Crude and Fuel Oil 4 2 200 210 410 860 #2 prog maint; #4 oil leak Nassirya Crude 4 3 165 160 110 435 600 #1 prog maint Najebia Natural Gas and Crude 2 1 88 88 160 #5 thrust bearing prob Hartha Natural Gas and Crude 4 1 180 180 300 #1 prog maint Out of Service for Unscheduled Maintanence Total: 1451 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance
# B- Gas_C-Power Stations
Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 2 180 125 Gas Oil Musil Dam Main 4 3 400 600 M. Baiji 8 1 20 Gas Oil Musil Dam reg 4 2 24 60 300 Quds 2 2 109 160 CO & GO Musil Pumping 2 0 Mosil 12 7 115 150 28 #1, #2 TF; #7 prog maint; #8 TF; #9 reverse power Haditha Dam 6 4 235 160 400 Dibis 3 2 53 30 29 #4 TF Samarra 3 3 45 55 590 Old Mulla 12 7 99 128 480 #1, #2 TF; #7 HET; #8 prog maint; #12 TF Himrin 2 2 35 21 135 New Mulla 6 4 116 173 3.1 #4 unstable load; #6 TF Hindia 4 4 5 5 120 Taji 7 55 #1, #2 NGPL; #3 TF; #4 NGPL; #5 HET; #6 prog maint; #7 TF Kufa 4 2 2 0 60 M. Taji 2 18 Gas Oil #2 software Total 746 896 Daura 4 30 #1, #2 NGPL; #3 needs rehab; #4 prog maint System Generation 71247 MWh Hilla 4 4 60 64 25 Syrian Line Generation 1377 MWh Najaf 3 3 115 129 23 Turkey Line Generation 2027 MWh Khor 4 3 131 80 Natural Gas #2 prog maint Total Generation 80078 MWh Shuaiba 2 2 7 20 Natural Gas System Peak Load 3377 MW M. Shuaiba 2 Natural Gas Syria Peak Load 60 MW Petro 4 0 Natural Gas Turkey Peak Load 82 MW M. Dibis 4 2 6 24 Natural Gas Fixed Gen Peak Load 266 MW Mossil East 5 3 17 0 Gas Oil Total Peak Load 3785 MW Hmam/Zafranya 7 Gas Oil Baghdad Load 1240 MW Diesel 70 Gas Oil Total 1098 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 Power transferred from North to Middle775 MW.
Power transferred from South to Middle 240 MW.
GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1240 24885 1037 1400 Duhok 82 1933 81 109 Naynawa 295 6494 271 491 Tamim 115 2909 121 181 Salah Aldeen 191 4541 189 247 Anbar 195 4214 176 233 Dyala 90 1999 83 134 Babil 90 2348 98 142 Kirbala 80 1811 75 107 Najaf 93 2126 89 128 Kadsya 60 1405 59 86 Wasit 87 1966 82 122 Muthana 55 1230 51 76 Nasirya 125 2533 106 128 Misan 65 1349 56 82 Basra 290 6549 273 317
Home / Essential Services / ESS-1b5658ba
Essential Services
System Status May 06
- Date
- 6 May 2004
- Category
- Essential Services
- Text available
- English
- Files
- 1
Spreadsheet preview
Sheet “A-Steam Power Stations”: 16 rows × 13 columns
| Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type Fuel | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load MW | Remarks | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | |||||||
| Dibis | Natural Gas | 4 | 1 | 8 | 8 | 24 | #2 DLL; #3 gen earth fault; #4 prog maint | |||||
| Baiji | Fuel Oil | 6 | 2 | 140 | 105 | 245 | 500 | #1, #3 prog maint; #4 stopped at 0010 under excit; #5 forced outage | ||||
| Daura | Fuel Oil | 4 | 0 | 180 | #3, #4 prog maint; #5, #6 rehab | |||||||
| South Baghdad | Fuel Oil | 6 | 3 | 30 | 30 | 25 | 85 | 200 | #1, #2, #3 prog maint | |||
| Mussaibe | Crude and Fuel Oil | 4 | 2 | 200 | 210 | 410 | 860 | #2 prog maint; #4 oil leak | ||||
| Nassirya | Crude | 4 | 3 | 165 | 160 | 110 | 435 | 600 | #1 prog maint | |||
| Najebia | Natural Gas and Crude | 2 | 1 | 88 | 88 | 160 | #5 thrust bearing prob | |||||
| Hartha | Natural Gas and Crude | 4 | 1 | 180 | 180 | 300 | #1 prog maint | |||||
| Out of Service for Unscheduled Maintanence | Total: | 1,451 | 2,824 | |||||||||
| Out of Service for Program Maintanence/Rehab | ||||||||||||
| No activity | ||||||||||||
| Not Performing at Peak Performance |
Sheet “B- Gas_C-Power Stations”: 27 rows × 13 columns
| Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 2 | 180 | 125 | Gas Oil | Musil Dam Main | 4 | 3 | 400 | 600 | ||
| M. Baiji | 8 | 1 | 20 | Gas Oil | Musil Dam reg | 4 | 2 | 24 | 60 | 300 | ||
| Quds | 2 | 2 | 109 | 160 | CO & GO | Musil Pumping | 2 | 0 | ||||
| Mosil | 12 | 7 | 115 | 150 | 28 | #1, #2 TF; #7 prog maint; #8 TF; #9 reverse power | Haditha Dam | 6 | 4 | 235 | 160 | 400 |
| Dibis | 3 | 2 | 53 | 30 | 29 | #4 TF | Samarra | 3 | 3 | 45 | 55 | 590 |
| Old Mulla | 12 | 7 | 99 | 128 | 480 | #1, #2 TF; #7 HET; #8 prog maint; #12 TF | Himrin | 2 | 2 | 35 | 21 | 135 |
| New Mulla | 6 | 4 | 116 | 173 | 3.10 | #4 unstable load; #6 TF | Hindia | 4 | 4 | 5 | 5 | 120 |
| Taji | 7 | 55 | #1, #2 NGPL; #3 TF; #4 NGPL; #5 HET; #6 prog maint; #7 TF | Kufa | 4 | 2 | 2 | 0 | 60 | |||
| M. Taji | 2 | 18 | Gas Oil | #2 software | Total | 746 | 896 | |||||
| Daura | 4 | 30 | #1, #2 NGPL; #3 needs rehab; #4 prog maint | System Generation | 71,247 | MWh | ||||||
| Hilla | 4 | 4 | 60 | 64 | 25 | Syrian Line Generation | 1,377 | MWh | ||||
| Najaf | 3 | 3 | 115 | 129 | 23 | Turkey Line Generation | 2,027 | MWh | ||||
| Khor | 4 | 3 | 131 | 80 | Natural Gas | #2 prog maint | Total Generation | 80,078 | MWh | |||
| Shuaiba | 2 | 2 | 7 | 20 | Natural Gas | System Peak Load | 3,377 | MW | ||||
| M. Shuaiba | 2 | Natural Gas | Syria Peak Load | 60 | MW | |||||||
| Petro | 4 | 0 | Natural Gas | Turkey Peak Load | 82 | MW | ||||||
| M. Dibis | 4 | 2 | 6 | 24 | Natural Gas | Fixed Gen Peak Load | 266 | MW | ||||
| Mossil East | 5 | 3 | 17 | 0 | Gas Oil | Total Peak Load | 3,785 | MW | ||||
| Hmam/Zafranya | 7 | Gas Oil | Baghdad Load | 1,240 | MW | |||||||
| Diesel | 70 | Gas Oil | ||||||||||
| Total | 1,098 | 1,186 | ||||||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
Sheet “Peak Loads”: 24 rows × 5 columns · preview of the first 21 rows; full file from the original button
| Reporting Peak for 05 MAY 2004 / Report Date - 06 MAY 2004 | ||||
|---|---|---|---|---|
| Power transferred from North to Middle775 MW. | ||||
| Power transferred from South to Middle 240 MW. | ||||
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | Demand Load MW |
| Baghdad | 1,240 | 24,885 | 1,037 | 1,400 |
| Duhok | 82 | 1,933 | 81 | 109 |
| Naynawa | 295 | 6,494 | 271 | 491 |
| Tamim | 115 | 2,909 | 121 | 181 |
| Salah Aldeen | 191 | 4,541 | 189 | 247 |
| Anbar | 195 | 4,214 | 176 | 233 |
| Dyala | 90 | 1,999 | 83 | 134 |
| Babil | 90 | 2,348 | 98 | 142 |
| Kirbala | 80 | 1,811 | 75 | 107 |
| Najaf | 93 | 2,126 | 89 | 128 |
| Kadsya | 60 | 1,405 | 59 | 86 |
| Wasit | 87 | 1,966 | 82 | 122 |
| Muthana | 55 | 1,230 | 51 | 76 |
| Nasirya | 125 | 2,533 | 106 | 128 |
| Misan | 65 | 1,349 | 56 | 82 |
| Basra | 290 | 6,549 | 273 | 317 |
Highlighting search results for: