Home / Essential Services / ESS-f0a85b02

Essential Services

DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 26, 2004

Date
26 April 2004
Category
Essential Services
Text available
English
Files
1
English original DOCDownload English text
DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 26, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: Qadisiyah and Kut-Nassirya 400 KV Transmission lines operational now. Generation: Peak Power 3931Mw, 76,763Mw hours, 7-day Avg. 3889Mw Generators Returned to Service: (7) 283 Mw Dibis 2, SP 8 Mw Nassirya 2 80 Mw Nassirya 4 100 Mw Mosil 3 15 Mw Hilla 5 15 Mw Khor Zubayr 4 50 Mw Shuaiba 2 15 Mw Generators Unscheduled Out of Service (20) 573 Mw PLANT Type SP, CP, RP, HP Fault Mw Dibis 3 SP Tripped-Ground/ Differential 8 South Baghdad 5 SP Boiler Leak 30 Najebia 5 SP Under Frequency 80 Baiji 1 CP Filter 85 Baiji Mobile, 4 CP No Fuel Filters 25 Doura 1,2 CP No gas pressure 40 Mosil 1 CP Rotor Defect 15 Mosil 2 CP Load Gear Oil leak 15 Mosil 9 CP Rotor Defect 15 Old Mulla 9 CP Load gear problems 15 New Mulla 4 CP Oil system problem 30 Qudas 2 CP Bearing problem 95 Shuaiba 1 CP Under Frequency 15 Shuaiba 2 CP Vibrations 15 Taji 1,2 CP No gas pressure 45 Taji 3, CP Compressor 15 Taji 5 CP High Exhaust Temp 15 M. Taji 2 CP Software 15 RED – Denotes out of service since last report Generators Scheduled Out of Service (26) 1318 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 1 SP M TBD 21 Mar 04 21 May 100 Baiji 3 SP M Bechtel 29 Feb 04 1 May 100 Dibis 4 SP M ME 15 Mar 04 30 Apr 8 Doura 4 CP M ME 14 Apr 04 31 May 20 Doura 3 CP R GRD/RIE 1 Mar 03 15 May 20 Doura 3 SP M ME 18 Mar 04 18 May 65 Doura 4 SP M ME 2 Feb 04 30 Apr 65 Doura 5 SP R Bechtel Jul 03 20 Jun 100 Doura 6 SP R Bechtel Jul 03 20 Jul 100 Dibis 4 CP R GRD/RIE Sep 03 12 May 30 Hartha 1 SP M ME 22 Mar 04 24 May 100 Khor Zubayr 2 CP R GRD/RIE 15 Mar 04 3 Jul 50 Mosil 7 CP M ME 24 Apr 04 TBD 15 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Nassirya 1 SP M ME 30 Mar 04 15 May 130 New Mulla 6 CP R GRD/RIE 28 Mar 04 15 May 30 Old Mulla 1 CP M ME 17 Apr 04 15 May 15 Old Mulla 2 CP M ME 17 Apr 04 15 May 15 Old Mulla 8 CP M ME 17 Apr 04 23 Apr 15 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 South Baghdad 1 SP M (Awaiting parts) ME 12 Feb 04 TBD 30 South Baghdad 2 SP M (Awaiting Parts) ME 12 Feb 04 TBD 30 South Baghdad 3 SP R ME 18 Mar 04 18 May 20 Taji 4 CP M ME 21 Apr 04 15 JUL 15 Taji 7 CP R GRD/RIE 1 Oct 03 15 JUL 15 Taji 6 CP M ME 2 Apr 04 26 May 15 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 129 towers complete/216req’d Haditha-Baghd West 400 Sabotage GRD/RIE Loading 246 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE Complete 23 Apr Operational Baiji - Baghd West #1 400 Sabotage GRD/RIE Complete Operational Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 15 Jun Dibis/Erbil-Qara Qosh 132 New Line GRD/RIE 15 May Contractor mobilized Dibis to Old Kirkuk 132 Reconductor GRD-RIE 30 Jun Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Jazair to Yarmook 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Baghd West – Jamia 132 Sabotage ME TBD Al Amarah-Burzulgan 132 Looting GRD-RIE 25 Jun 26 towers complete /126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: Distribution: Power transferred from North to Middle 930 MW. Power transferred from South to Middle 180 MW. GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1350 25121 1047 1369 Duhok 82 1929 80 116 Naynawa 350 7138 297 500 Tamim 145 3086 129 181 Salah Aldeen 220 4230 176 241 Anbar 200 4029 168 231 Dyala 90 1844 77 131 Babil 115 2061 86 135 Kirbala 85 1884 79 111 Najaf 115 2049 85 122 Kadsya 65 1274 53 87 Wasit 100 1967 82 114 Muthana 60 1262 53 75 Nasirya 120 2141 89 116 Misan 65 1275 53 78 Basra 215 4687 195 208 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 1 of NUMPAGES 3