REPORT DATE - 19 DECEMBER 2003
A - Steam Power Stations
Power StationsTypeNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget LoadRemarks
Fuel123456MW
DibisNatural Gas400000024No.1 mnt 10 DEC to 25 JAN. No. 2 and 3 FWP. No 3 Tripped oil system. No 4 Tripped HET.
BaijiFuel Oil63085859000260500No. 5 rehab. No. 6 mnt 5 DEC to 19 JAN. No. 1 tripped boiler leakage.
DuraFuel Oil418000080180No. 4 Mnt 10 OCT to 12 DEC. Nos. 5 & 6: Rehab.
South BaghdadFuel Oil6330253000085200No. 6 mnt 11 NOV to 26 DEC. No. 5 mnt 1 DEC to 15 JAN. No. 4 boiler leakage.
MussaibeCrude and Fuel Oil4201600220380860No. 3 program mnt 3 NOV to 18 DEC. No. 1 boiler leak.
NassiryaCrude431451450130420600No. 3 mnt 11 NOV to 15 DEC.
NajebiaNatural Gas and Crude2109090160No. 4 mnt 4 NOV to 22 DEC.
HarthaNatural Gas and Crude411400140300No. 4 Mnt from 23 OCT to 23 DEC.
Total:1,4552,824
# A-Steam Power Stations REPORT DATE - 19 DECEMBER 2003 A - Steam Power Stations Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 0 0 0 0 0 0 24 No.1 mnt 10 DEC to 25 JAN. No. 2 and 3 FWP. No 3 Tripped oil system. No 4 Tripped HET. Baiji Fuel Oil 6 3 0 85 85 90 0 0 260 500 No. 5 rehab. No. 6 mnt 5 DEC to 19 JAN. No. 1 tripped boiler leakage. Dura Fuel Oil 4 1 80 0 0 0 80 180 No. 4 Mnt 10 OCT to 12 DEC. Nos. 5 & 6: Rehab. South Baghdad Fuel Oil 6 3 30 25 30 0 0 0 85 200 No. 6 mnt 11 NOV to 26 DEC. No. 5 mnt 1 DEC to 15 JAN. No. 4 boiler leakage. Mussaibe Crude and Fuel Oil 4 2 0 160 0 220 380 860 No. 3 program mnt 3 NOV to 18 DEC. No. 1 boiler leak. Nassirya Crude 4 3 145 145 0 130 420 600 No. 3 mnt 11 NOV to 15 DEC. Najebia Natural Gas and Crude 2 1 0 90 90 160 No. 4 mnt 4 NOV to 22 DEC. Hartha Natural Gas and Crude 4 1 140 0 140 300 No. 4 Mnt from 23 OCT to 23 DEC. Total: 1455 2824 # B- Gas_C-Power Stations Report Date- 19 DECEMBER 2003 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 120 125 Gas Oil No. 2 lub oil leak. Musil Dam Main 4 3 306 600 Quds 2 2 230 160 Gas Oil 39 trucks. Musil Dam reg 4 3 36 60 450 Mosil 12 9 145 150 30 No. 1 Rotor Defect. No. 3 Prog Maint. No. 4 Vibration Musil Pumping 2 0 0 0 Dibis 3 0 0 60 0 No. 4, 5& 6 rehab. Haditha Dam 6 2 150 160 480 Old Mulla 12 5 70 128 520 No. 1 gas control. No. 2 servo and C/B. No. 5 Programmed Mnt. No. 12 rehab. No. 6 tripped acc gear. No. 7 Prog Maint. Samarra 3 2 38 55 390 New Mulla 6 3 105 173 400 No. 2 Tripped Gas Leak. No. 4 Cooling Pump. No. 6 Generator Defective. Himrin 2 1 19 21 Taji 7 3 50 55 18 No. 3 Compressor. No. 4 Turbine. No. 5 Flame. No. 7 Rehab. Hindia 4 3 5 5 M. Taji 2 0 0 20 0 No. 1 & 2 software. Kufa 4 0 0 1 Dura 4 3 70 30 17 No.3 Rehabilitation. Total 554 896 Hilla 4 0 0 64 0 LNG Pressure. System Generation 65997 MWh Najaf 3 1 27 129 Gas Oil No. 2 program mnt. LNG Pressure. Syrian Line Generation 1276 MWh Khor 4 3 120 80 Natural Gas No. 4: Rehabilitation. Turkey Line Generation 1650 MWh Shuaiba 2 1 5 20 Natural Gas No 2 VIB. Total Generation 68823 MWh Petro 4 1 10 0 Natural Gas System Peak Load 3036 MW M. Dibis 4 0 0 24 Natural Gas Syria Peak Load 20 MW Mossil East 5 0 0 15 Gas Oil Turkey Peak Load 80 MW Hmam/Zafranya 7 0 0 Gas Oil Fixed Gen Peak Load 77 MW Diesel 0 Total Peak Load 3213 MW Total 952 1233 Baghdad Load 1150 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads GOVERNORATE Peak Load MW MWH Average Load MW 19 December, 2003 Baghdad 1100 24000 1000 Power transferred from North to Middle 610 MW. Duhok 80 1649 68.7083 Naynawa 300 6914 288.0833 Power transferred from South to Middle 120 MW. Tamim 121 3150 131.25 Salah Aldeen 150 3764 156.8333 Anbar 180 3486 145.25 Dyala 75 1192 49.6667 Babil 85 1678 69.9167 Kirbala 70 1286 53.5833 Najaf 75 1365 56.875 Kadsya 65 1107 46.125 Wasit 75 1469 61.2083 Muthana 55 1122 46.75 Nasirya 100 2631 109.625 Misan 60 1192 49.6667 Basra 300 6739 280.7917 2891 MWH not provided by Ministry of Electricity