DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 28, 2004
The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site.
HIGHLIGHTS: Starting to see the increase in generation as units return from maintenance.
Generation:
Peak Power 4251Mw, 82,283Mw hours, 7-day Avg. 4012Mw Generators Returned to Service: (3) 130 Mw South Baghdad 4 30 Mw Baiji 1, CP 85 Mw Shuaiba 1 15 Mw Generators Unscheduled Out of Service (12) 260 Mw PLANT
Type
SP, CP, RP, HP
Fault
Mw
Baiji Mobile, 4
CP
Fuel Filters
25
* Dibis 5
CP
Turbine vibrations
30
Doura 1,2
CP
No gas pressure
40
Mosil 1
CP
Rotor Defect
15
Mosil 2
CP
Load Gear Oil leak
15
Mosil 9
CP
Rotor Defect
15
Old Mulla 7
CP
High exhaust temp
15
Shuaiba 2
CP
Vibrations
15
Taji 1,2
CP
No gas pressure
45
Taji 3,
CP
Compressor
15
Taji 5
CP
High Exhaust Temp
15
M. Taji 2
CP
Software
15
RED – Denotes out of service since last report
Generators Scheduled Out of Service (30) 1437 Mw PLANT
Type
SP/NG
Prog. Maintenance(M) / Rehab (R) Maint.
Org.
Date out-of -service
Est. In-service Date
Mw
Baiji 1
SP
M
ME
21 Mar 04
21 May
100
Baiji 2
SP
M
ME
26 Apr 04
29 Apr
95
Baiji 3
SP
M
Bechtel
29 Feb 04
1 May
100
Dibis 1
SP
M
ME
26 Apr 04
1 May
8
Dibis 2
SP
M
ME
26 Apr 04
1 May
8
Dibis 3
SP
M
ME
26 Apr 04
1 May
8
Dibis 4
SP
M
ME
15 Mar 04
30 Apr
8
Doura 4
CP
M
ME
14 Apr 04
31 May
20
Doura 3
CP
R
GRD/RIE
1 Mar 03
15 May
20
Doura 3
SP
M
ME
18 Mar 04
18 May
65
Doura 4
SP
M
ME
2 Feb 04
30 Apr
65
Doura 5
SP
R
Bechtel
Jul 03
20 Jun
100
Doura 6
SP
R
Bechtel
Jul 03
20 Jul
100
Dibis 4
CP
R
GRD/RIE
Sep 03
12 May
30
Hartha 1
SP
M
ME
22 Mar 04
23 May
100
Khor Zubayr 2
CP
R
GRD/RIE
15 Mar 04
3 Jul
50
Mosil 7
CP
M
ME
24 Apr 04
TBD
15
Mussaibe 2
SP
M
ME
28 Feb 04
28 Apr
200
Nassirya 1
SP
M
ME
30 Mar 04
15 May
130
New Mulla 6
CP
R
GRD/RIE
28 Mar 04
15 May
30
Old Mulla 1
CP
M
ME
17 Apr 04
15 May
15
Old Mulla 2
CP
M
ME
17 Apr 04
15 May
15
Old Mulla 8
CP
M
ME
17 Apr 04
23 Apr
15
Old Mulla 12
CP
R
GRD/RIE
1 Oct 03
15 May
15
South Baghdad 1
SP
M (Awaiting parts)
ME
12 Feb 04
TBD
30
South Baghdad 2
SP
M (Awaiting Parts)
ME
12 Feb 04
TBD
30
South Baghdad 3
SP
R
ME
18 Mar 04
18 May
20
Taji 4
CP
M
ME
21 Apr 04
15 JUL
15
Taji 7
CP
R
GRD/RIE
1 Oct 03
15 JUL
15
Taji 6
CP
M
ME
2 Apr 04
26 May
15
LEGEND OF ELECTRICAL SYSTEM POWER SOURCE
SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER
Transmission:
LINE
Kv
Fault
Maint.
Org.
Date out-of -service
Est. In-service Date
Comments
Nassiriya-Khor Zubayr
400
Sabotage
Bechtel
26 May
129 towers complete/216req’d Haditha-Baghd West 400 Sabotage GRD/RIE
Complete
246 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE
Complete
23 Apr Operational
Baiji - Baghd West #1
400
Sabotage
GRD/RIE
Complete
Operational
Baghd E.-Baghd S. #2
400
New Line
GRD/RIE
Complete
81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE
TBD
No contract awarded
Baiji – Haditha
400
Sabotage
Bechtel
TBD
No contract awarded
Diyala Connection
400
New Line
ME
15 Jun
Dibis/Erbil-Qara Qosh
132
New Line
GRD/RIE
15 May
Construction ongoing
Dibis to Old Kirkuk
132
Reconductor
GRD-RIE
30 Jun
Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME
TBD
Shuwaiba-Toba-Hamar
132
Sabotage
ME
Complete
44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE
5 Jul
Assessment underway
Jazair to Yarmook
132
Reconductor
GRD-RIE
1 Jul
Assessment underway
Baghd West – Jamia
132
Sabotage
ME
TBD
Old Amarah-Burzulgan
132
Looting
GRD-RIE
25 Jun
Assessment underway
Temim- Tuz
132
Sabotage
ME
TBD
Nejibiya – Hartha
132
Sabotage
ME
TBD
Lines Returned to service:
Distribution:
Power transferred from North to Middle 940 MW.
Power transferred from South to Middle 230 MW.
GOVERNORATE
Peak Load MW
MWH
Average Load MW
Demand Load MW
Baghdad
1350
29940
1248
1439
Duhok
80
1918
80
105
Naynawa
385
8019
334
488
Tamim
145
3221
134
175
Salah Aldeen
210
4880
203
243
Anbar
210
4184
174
213
Dyala
100
2197
92
130
Babil
105
2251
94
138
Kirbala
102
2109
88
110
Najaf
115
2435
101
126
Kadsya
70
1508
63
84
Wasit
75
2111
88
114
Muthana
58
1358
57
75
Nasirya
130
2593
108
125
Misan
60
1306
54
80
Basra
300
6461
269
284
Data compiled and reported by:
LTC Tharnell M. Thomas
CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 1 of NUMPAGES 3
Home / Essential Services / ESS-b43e84df
Essential Services