Report Date - 18 FEBRUARY 2004
A - Steam Power Stations
Power StationsType FuelNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget Load MWRemarks
123456
DibisNatural Gas418824#2 boiler leakage; #3 prog maint; #4 boiler leakage
BaijiFuel Oil639080120290500#2 prog maint; #3 synch at 1507, stopped at 1704 under excit; #5 forced outage
DauraFuel Oil417575180#4 prog maint; #5 & #6 rehab
South BaghdadFuel Oil6320303080200#1 & #2 prog maint; #5 synch at 1105; #6 thurst bearing test
MussaibeCrude and Fuel Oil42195195390860#1 stopped at 650 ehg; #4 prog maint
NassiryaCrude43150160150460600#1 cond. cleaning
NajebiaNatural Gas and Crude2280100180160
HarthaNatural Gas and Crude41130130300#4 prog maint
Out of Service for Unscheduled MaintanenceTotal:1,6132,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations Report Date - 18 FEBRUARY 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 1 8 8 24 #2 boiler leakage; #3 prog maint; #4 boiler leakage Baiji Fuel Oil 6 3 90 80 120 290 500 #2 prog maint; #3 synch at 1507, stopped at 1704 under excit; #5 forced outage Daura Fuel Oil 4 1 75 75 180 #4 prog maint; #5 & #6 rehab South Baghdad Fuel Oil 6 3 20 30 30 80 200 #1 & #2 prog maint; #5 synch at 1105; #6 thurst bearing test Mussaibe Crude and Fuel Oil 4 2 195 195 390 860 #1 stopped at 650 ehg; #4 prog maint Nassirya Crude 4 3 150 160 150 460 600 #1 cond. cleaning Najebia Natural Gas and Crude 2 2 80 100 180 160 Hartha Natural Gas and Crude 4 1 130 130 300 #4 prog maint Out of Service for Unscheduled Maintanence Total: 1613 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Report Date - 18 FEBRUARY 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 85 125 Gas Oil #2 lub oil leak from bearing Musil Dam Main 4 4 555 600 Quds 2 2 204 160 Gas Oil 30 trucks - #2 synch at 1555 Musil Dam reg 4 4 27 60 1000 Mosil 12 5 60 150 18 #1 rotor defect; #2 synch 705; #3 synch 705, no load; #4, #5, #6 over voltage; #7 over voltage, synch at 710; #9 rotor defect; #10 over voltage, synch at 710; #12 over voltage, synch at 720 Musil Pumping 2 1 110 0 Dibis 3 2 54 30 28 #4 rehab Haditha Dam 6 2 125 160 350 Old Mulla 12 7 110 128 450 #1 acc gear; #2 servo; #5 prog maint; #10 prog maint; #12 needs rehab Samarra 3 2 40 55 440 New Mulla 6 3 110 173 3 #1 & #2 prog maint; #6 generator defect Himrin 2 2 42 21 160 Taji 7 4 61 55 15 #3 compressor; #7 needs rehab Hindia 4 4 5 5 100 M. Taji 2 18 #2 software Kufa 4 0 Daura 4 1 10 30 12 #3 needs rehab; #4 g.p.l. Total 904 896 Hilla 4 2 35 64 34 #1 cooling sys prob; #2 servo System Generation 82955 MWh Najaf 3 2 90 129 32 #2 synch for test at 1615, stopped at 1626 Syrian Line Generation 1283 MWh Khor 4 3 140 80 Natural Gas #4 rehab Turkey Line Generation 1959 MWh Shuaiba 2 1 4 20 Natural Gas #1 prog maint Total Generation 91624 MWh M. Shuaiba 2 Natural Gas split with the refinery System Peak Load 3794 MW Petro 4 1 10 0 Natural Gas Syria Peak Load 55 MW M. Dibis 4 24 Natural Gas Turkey Peak Load 82 MW Mossil East 5 3 17 0 Gas Oil Fixed Gen Peak Load 266 MW Hmam/Zafranya 7 2 3 Gas Oil Total Peak Load 4197 MW Diesel 51 Gas Oil Baghdad Load 1545 MW Total 1044 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Report Date - 18 FEBRUARY 2004 GOVERNORATE Peak Load MW MWH Average Load MW Baghdad 1545 Duhok 82 Naynawa 350 Tamim 124 Salah Aldeen 210 Anbar 210 Dyala 95 Babil 96 Kirbala 100 Najaf 102 Kadsya 57 Wasit 90 Muthana 65 Nasirya 130 Misan 85 Basra 345