# A-Steam Power Stations
REPORT DATE -19 NOVEMBER 2003
A - Steam Power Stations
Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 1 0 0 8 0 8 24 No. 2 Boiler Leakage. No. 1 stopped FWP. No. 4 tripped at 0035 DLL.
Baiji Fuel Oil 6 4 110 80 70 0 0 85 345 500 No. 5 rehab. No. 4 boiler leak.
Dura Fuel Oil 4 1 75 0 0 0 75 180 No. 4: Programmed Maintenance10 OCT to 25 NOV. Nos. 5 & 6: Rehabilitation.
South Baghdad Fuel Oil 6 3 40 0 30 0 35 0 105 200 No.2 stop valve. No. 3 synch at 1244. No. 6 programmed mnt 11 NOV to 26 DEC. No. 4 hydraulic.
Mussaibe Crude and Fuel Oil 4 2 140 0 0 215 355 860 No. 2 program mnt 20 OCT to 12 NOV. No. 3 program mnt 5 NOV to 20 DEC. No. 1 limited to AVR.
Nassirya Crude 4 2 130 140 0 0 270 600 No. 3 programmed mnt 11 NOV to 11 DEC. No. 4 expan.
Najebia Natural Gas and Crude 2 1 0 80 80 160 No. 4 programmed mnt 6 NOV to 21 DEC.
Hartha Natural Gas and Crude 4 1 110 0 110 300 No. 4 Programmed Maintenance from 23 OCT to 23 DEC.
Total: 1348 2824
# B- Gas_C-Power Stations
Report Date- 19 NOVEMBER 2003 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 135 125 Gas Oil No. 1 s/b. Musil Dam Main 4 2 160 600 Quds 2 2 200 160 Gas Oil 41 trucks. Musil Dam reg 4 3 32 60 450 Mosil 12 7 110 150 32 No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. No. 3 control cards. No. 6 oil pump. Musil Pumping 2 0 0 0 Dibis 3 0 0 60 32 No. 5 problem turbine rotor. No. 6: Programmed Maintenance. No. 4 rotor defect. Haditha Dam 6 2 100 160 300 Old Mulla 12 7 95 128 32 No. 1 gas control. No. 2 gen protec. No. 5 Programmed Mnt. No. 12 rehab. No. 6 gene. Prot. Samarra 3 3 55 55 540 New Mulla 6 3 105 173 32 No. 6 Generator Defective. No. 4 cooling fan. Himrin 2 2 35 21 130 Taji 7 4 65 55 18 No. 5 Diesel. No.7 Rehabilitation. No. 2 excit. Hindia 4 4 5 5 220 M. Taji 2 0 0 20 0 NGPL Kufa 4 0 0 1 Dura 4 1 20 30 18 No.3 Rehabilitation. No. 4 turbine vibration. Total 387 896 Hilla 4 4 65 64 24 System Generation 67148 MWh Najaf 3 3 120 129 22 Syrian Line Generation 1309 MWh Khor 4 3 96 80 Natural Gas No. 4: Rehabilitation. Turkey Line Generation 2562 MWh Shuaiba 2 1 3 20 Natural Gas No. 1 Programmed Maintenance. Total Generation 71019 MWh Petro 4 1 0 0 Natural Gas System Peak Load 3343 MW M. Dibis 4 0 0 24 Natural Gas Syria Peak Load 60 MW Mossil East 5 0 0 15 Gas Oil Turkey Peak Load 108 MW Hmam 2 0 0 Gas Oil Fixed Gen Peak Load 77 MW Total Peak Load 3588 MW Total 1014 1233 Baghdad Load 1220 MW Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590).
Edited by Electricity Commission U.S. Advisor Staff.
# Peak Loads
GOVERNORATE Peak Load MW MWH Average Load MW 19 NOVEMBER, 2003 Baghdad 1220 24059 1002.4583 Power transferred from North to Middle 765 MW Duhok 108 2265 94.375 Naynawa 327 7638 318.25 Power transferred from South to Middle 100 MW Tamim 148 3798 158.25 Salah Aldeen 210 4690 195.4167 Anbar 170 3632 151.3333 Dyala 80 1632 68 Babil 95 2015 83.9583 Kirbala 75 1604 66.8333 Najaf 80 1942 80.9167 Kadsya 65 1497 62.375 Wasit 85 1739 72.4583 Muthana 55 1311 54.625 Nasirya 110 2471 102.9583 Misan 55 1337 55.7083 Basra 250 6487 270.2917 3133
Home / Essential Services / ESS-3fed09ff
Essential Services
power system20nov03
- Date
- 19 November 2003
- Category
- Essential Services
- Text available
- English
- Files
- 1
Spreadsheet preview
Sheet “A-Steam Power Stations”: 13 rows × 13 columns
| REPORT DATE -19 NOVEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A - Steam Power Stations | ||||||||||||
| Power Stations | Type | No. of Units | No. of Operating Units | Units Load (MW) | Total Load MW | Target Load | Remarks | |||||
| Fuel | 1 | 2 | 3 | 4 | 5 | 6 | MW | |||||
| Dibis | Natural Gas | 4 | 1 | 0 | 0 | 8 | 0 | 8 | 24 | No. 2 Boiler Leakage. No. 1 stopped FWP. No. 4 tripped at 0035 DLL. | ||
| Baiji | Fuel Oil | 6 | 4 | 110 | 80 | 70 | 0 | 0 | 85 | 345 | 500 | No. 5 rehab. No. 4 boiler leak. |
| Dura | Fuel Oil | 4 | 1 | 75 | 0 | 0 | 0 | 75 | 180 | No. 4: Programmed Maintenance10 OCT to 25 NOV. Nos. 5 & 6: Rehabilitation. | ||
| South Baghdad | Fuel Oil | 6 | 3 | 40 | 0 | 30 | 0 | 35 | 0 | 105 | 200 | No.2 stop valve. No. 3 synch at 1244. No. 6 programmed mnt 11 NOV to 26 DEC. No. 4 hydraulic. |
| Mussaibe | Crude and Fuel Oil | 4 | 2 | 140 | 0 | 0 | 215 | 355 | 860 | No. 2 program mnt 20 OCT to 12 NOV. No. 3 program mnt 5 NOV to 20 DEC. No. 1 limited to AVR. | ||
| Nassirya | Crude | 4 | 2 | 130 | 140 | 0 | 0 | 270 | 600 | No. 3 programmed mnt 11 NOV to 11 DEC. No. 4 expan. | ||
| Najebia | Natural Gas and Crude | 2 | 1 | 0 | 80 | 80 | 160 | No. 4 programmed mnt 6 NOV to 21 DEC. | ||||
| Hartha | Natural Gas and Crude | 4 | 1 | 110 | 0 | 110 | 300 | No. 4 Programmed Maintenance from 23 OCT to 23 DEC. | ||||
| Total: | 1,348 | 2,824 |
Sheet “B- Gas_C-Power Stations”: 25 rows × 13 columns
| Report Date- 19 NOVEMBER 2003 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B- Gas Power Stations | C -Hydro Power Stations | |||||||||||
| Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Fuel Use | Remarks | Power Stations | No. of Units | No. of Operating Units | Station Load | Target Load | Discharge m3/Sec |
| Gas Pressure | ||||||||||||
| Baiji | 2 | 1 | 135 | 125 | Gas Oil | No. 1 s/b. | Musil Dam Main | 4 | 2 | 160 | 600 | |
| Quds | 2 | 2 | 200 | 160 | Gas Oil | 41 trucks. | Musil Dam reg | 4 | 3 | 32 | 60 | 450 |
| Mosil | 12 | 7 | 110 | 150 | 32 | No. 1 rotor defect. No. 2 ACC. No. 8 program mnt. No. 3 control cards. No. 6 oil pump. | Musil Pumping | 2 | 0 | 0 | 0 | |
| Dibis | 3 | 0 | 0 | 60 | 32 | No. 5 problem turbine rotor. No. 6: Programmed Maintenance. No. 4 rotor defect. | Haditha Dam | 6 | 2 | 100 | 160 | 300 |
| Old Mulla | 12 | 7 | 95 | 128 | 32 | No. 1 gas control. No. 2 gen protec. No. 5 Programmed Mnt. No. 12 rehab. No. 6 gene. Prot. | Samarra | 3 | 3 | 55 | 55 | 540 |
| New Mulla | 6 | 3 | 105 | 173 | 32 | No. 6 Generator Defective. No. 4 cooling fan. | Himrin | 2 | 2 | 35 | 21 | 130 |
| Taji | 7 | 4 | 65 | 55 | 18 | No. 5 Diesel. No.7 Rehabilitation. No. 2 excit. | Hindia | 4 | 4 | 5 | 5 | 220 |
| M. Taji | 2 | 0 | 0 | 20 | 0 | NGPL | Kufa | 4 | 0 | 0 | 1 | |
| Dura | 4 | 1 | 20 | 30 | 18 | No.3 Rehabilitation. No. 4 turbine vibration. | Total | 387 | 896 | |||
| Hilla | 4 | 4 | 65 | 64 | 24 | System Generation | 67,148 | MWh | ||||
| Najaf | 3 | 3 | 120 | 129 | 22 | Syrian Line Generation | 1,309 | MWh | ||||
| Khor | 4 | 3 | 96 | 80 | Natural Gas | No. 4: Rehabilitation. | Turkey Line Generation | 2,562 | MWh | |||
| Shuaiba | 2 | 1 | 3 | 20 | Natural Gas | No. 1 Programmed Maintenance. | Total Generation | 71,019 | MWh | |||
| Petro | 4 | 1 | 0 | 0 | Natural Gas | System Peak Load | 3,343 | MW | ||||
| M. Dibis | 4 | 0 | 0 | 24 | Natural Gas | Syria Peak Load | 60 | MW | ||||
| Mossil East | 5 | 0 | 0 | 15 | Gas Oil | Turkey Peak Load | 108 | MW | ||||
| Hmam | 2 | 0 | 0 | Gas Oil | Fixed Gen Peak Load | 77 | MW | |||||
| Total Peak Load | 3,588 | MW | ||||||||||
| Total | 1,014 | 1,233 | Baghdad Load | 1,220 | MW | |||||||
| Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). | ||||||||||||
| Edited by Electricity Commission U.S. Advisor Staff. |
Sheet “Peak Loads”: 21 rows × 5 columns · preview of the first 19 rows; full file from the original button
| GOVERNORATE | Peak Load MW | MWH | Average Load MW | 19 NOVEMBER, 2003 |
|---|---|---|---|---|
| Baghdad | 1,220 | 24,059 | 1,002.46 | Power transferred from North to Middle 765 MW |
| Duhok | 108 | 2,265 | 94.38 | |
| Naynawa | 327 | 7,638 | 318.25 | Power transferred from South to Middle 100 MW |
| Tamim | 148 | 3,798 | 158.25 | |
| Salah Aldeen | 210 | 4,690 | 195.42 | |
| Anbar | 170 | 3,632 | 151.33 | |
| Dyala | 80 | 1,632 | 68 | |
| Babil | 95 | 2,015 | 83.96 | |
| Kirbala | 75 | 1,604 | 66.83 | |
| Najaf | 80 | 1,942 | 80.92 | |
| Kadsya | 65 | 1,497 | 62.38 | |
| Wasit | 85 | 1,739 | 72.46 | |
| Muthana | 55 | 1,311 | 54.62 | |
| Nasirya | 110 | 2,471 | 102.96 | |
| Misan | 55 | 1,337 | 55.71 | |
| Basra | 250 | 6,487 | 270.29 | |
| 3,133 |