DAILY POWER SYSTEM HIGHLIGHTS FOR MAY 3, 2004
The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site.
HIGHLIGHTS: Starting to see the increase in generation as units return from maintenance.
Generation:
Peak Power 3933Mw, 80,309Mw hours, 7-day Avg. 4154Mw Generators Returned to Service: (1) 100 Mw Nassirya 4 100 Mw
Generators Unscheduled Out of Service (16) 410 Mw PLANT
Type
SP, CP, RP, HP
Fault
Mw
* Najebia 5
SP
Thrust bearing problem
80
South Baghdad 5
SP
Boiler Leak
30
Baiji Mobile, 4
CP
Fuel Filters
25
Doura 1,2
CP
No gas pressure
40
Mosil 1
CP
Rotor Defect
15
* Mosil 3
CP
Stopped-contractor request 15 Mosil 9 CP Reverse Power 15
* New Mulla 4
CP
Unstable Load
30
Old Mulla 7
CP
High exhaust temp
15
* Qudas 1
CP
Filter Cleaning
70
Taji 1,2
CP
No gas pressure
30
Taji 3,
CP
Compressor
15
Taji 5
CP
High Exhaust Temp
15
M. Taji 2
CP
Software
15
RED – Denotes out of service since last report
Generators Scheduled Out of Service (29) 1451 Mw PLANT
Type
SP/NG
Prog. Maintenance(M) / Rehab (R) Maint.
Org.
Date out-of -service
Est. In-service Date
Mw
Baiji 1
SP
M
Bechtel
21 Mar 04
21 May
100
Baiji 2
SP
M
Bechtel
26 Apr 04
3 May
95
Baiji 3
SP
M(Additional work)
Bechtel
29 Feb 04
3 May
100
Dibis 3
SP
M
ME
26 Apr 04
5 May
8
Dibis 4
SP
M
ME
15 Mar 04
5 May
8
Doura 4
CP
M
ME
14 Apr 04
31 May
20
Doura 3
CP
R
ME
1 Mar 03
TBD
20
Doura 3
SP
M
ME
18 Mar 04
18 May
65
Doura 4
SP
M
ME
2 Feb 04
TBD
65
Doura 5
SP
R
Bechtel
Jul 03
20 Jun
100
Doura 6
SP
R
Bechtel
Jul 03
20 Jul
100
Dibis 4
CP
R
GRD/RIE
Sep 03
12 May
30
Hartha 1
SP
M
ME
22 Mar 04
23 May
100
Khor Zubayr 2
CP
R
GRD/RIE
15 Mar 04
3 Jul
50
Mosil 7
CP
M
ME
24 Apr 04
TBD
15
Mussaibe 2
SP
M (additional work)
ME
28 Feb 04
20 May
200
Najaf 2
CP
M
ME
1 May 04
TBD
30
Nassirya 1
SP
M
ME
30 Mar 04
15 May
130
New Mulla 6
CP
R
GRD/RIE
28 Mar 04
15 May
30
Old Mulla 1
CP
M
ME
17 Apr 04
15 May
15
Old Mulla 2
CP
M
ME
17 Apr 04
15 May
15
Old Mulla 8
CP
M
ME
17 Apr 04
TBD
15
Old Mulla 12
CP
R
GRD/RIE
1 Oct 03
15 May
15
South Baghdad 1
SP
M (Awaiting parts)
ME
12 Feb 04
31 May
30
South Baghdad 2
SP
M (Awaiting Parts)
ME
12 Feb 04
31 May
30
South Baghdad 3
SP
R
ME
18 Mar 04
18 May
20
Taji 4
CP
M
GRD/RIE
21 Apr 04
15 JUL
15
Taji 7
CP
R
GRD/RIE
1 Oct 03
15 JUL
15
Taji 6
CP
M
ME
2 Apr 04
26 May
15
New In-service date
LEGEND OF ELECTRICAL SYSTEM POWER SOURCE
SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER
Transmission:
LINE
Kv
Fault
Maint.
Org.
Date out-of -service
Est. In-service Date
Comments
Nassiriya-Khor Zubayr
400
Sabotage
Bechtel
26 May
129 towers complete/216req’d Haditha-Baghd West 400 Sabotage GRD/RIE
Complete
246 towers complete/246 req’d Hartha-Qut Wasit 400 Sabotage GRD/RIE
Complete
23 Apr Operational
Baiji - Baghd West #1
400
Sabotage
GRD/RIE
Complete
Operational
Baghd E.-Baghd S. #2
400
New Line
GRD/RIE
Complete
81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE
TBD
No contract awarded
Baiji – Haditha
400
Sabotage
Bechtel
TBD
No contract awarded
Diyala Connection
400
New Line
ME
15 Jun
Dibis/Erbil-Qara Qosh
132
New Line
GRD/RIE
22 May
Construction ongoing
Dibis to Old Kirkuk
132
Reconductor
GRD-RIE
31 Jul
Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME
TBD
Shuwaiba-Toba-Hamar
132
Sabotage
ME
Complete
44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE
5 Jul
Assessment underway
Jazair to Yarmook
132
Reconductor
GRD-RIE
5 Jul
Assessment underway
Baghd West – Jamia
132
Sabotage
ME
TBD
Old Amarah-Burzulgan
132
Looting
GRD-RIE
25 Jun
Assessment underway
Temim- Tuz
132
Sabotage
ME
TBD
Nejibiya – Hartha
132
Sabotage
ME
TBD
Lines Returned to service:
Distribution: No report today Power transferred from North to Middle 710 MW.
Power transferred from South to Middle 160 MW.
GOVERNORATE
Peak Load MW
MWH
Average Load MW
Demand Load MW
Baghdad
1400
27461
1144
1471
Duhok
84
1903
79
112
Naynawa
400
7496
312
477
Tamim
160
3029
126
177
Salah Aldeen
223
4674
195
246
Anbar
195
4141
173
238
Dyala
104
2167
90
135
Babil
114
2211
92
135
Kirbala
89
1801
75
110
Najaf
119
2274
95
136
Kadsya
65
1282
53
85
Wasit
90
1946
81
122
Muthana
60
1297
54
78
Nasirya
126
2565
107
133
Misan
67
1457
61
79
Basra
350
6725
280
294
Data compiled and reported by:
LTC Tharnell M. Thomas
CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 3 of NUMPAGES 3
Home / Essential Services / ESS-27160624
Essential Services