DAILY POWER SYSTEM HIGHLIGHTS FOR MAY 3, 2004

Date
3 May 2004
Category
Essential Services
Text available
English
Files
1
English original DOCDownload English text
DAILY POWER SYSTEM HIGHLIGHTS FOR MAY 3, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: Starting to see the increase in generation as units return from maintenance. Generation: Peak Power 3933Mw, 80,309Mw hours, 7-day Avg. 4154Mw Generators Returned to Service: (1) 100 Mw Nassirya 4 100 Mw Generators Unscheduled Out of Service (16) 410 Mw PLANT Type SP, CP, RP, HP Fault Mw * Najebia 5 SP Thrust bearing problem 80 South Baghdad 5 SP Boiler Leak 30 Baiji Mobile, 4 CP Fuel Filters 25 Doura 1,2 CP No gas pressure 40 Mosil 1 CP Rotor Defect 15 * Mosil 3 CP Stopped-contractor request 15 Mosil 9 CP Reverse Power 15 * New Mulla 4 CP Unstable Load 30 Old Mulla 7 CP High exhaust temp 15 * Qudas 1 CP Filter Cleaning 70 Taji 1,2 CP No gas pressure 30 Taji 3, CP Compressor 15 Taji 5 CP High Exhaust Temp 15 M. Taji 2 CP Software 15 RED – Denotes out of service since last report Generators Scheduled Out of Service (29) 1451 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 1 SP M Bechtel 21 Mar 04 21 May 100 Baiji 2 SP M Bechtel 26 Apr 04 3 May 95 Baiji 3 SP M(Additional work) Bechtel 29 Feb 04 3 May 100 Dibis 3 SP M ME 26 Apr 04 5 May 8 Dibis 4 SP M ME 15 Mar 04 5 May 8 Doura 4 CP M ME 14 Apr 04 31 May 20 Doura 3 CP R ME 1 Mar 03 TBD 20 Doura 3 SP M ME 18 Mar 04 18 May 65 Doura 4 SP M ME 2 Feb 04 TBD 65 Doura 5 SP R Bechtel Jul 03 20 Jun 100 Doura 6 SP R Bechtel Jul 03 20 Jul 100 Dibis 4 CP R GRD/RIE Sep 03 12 May 30 Hartha 1 SP M ME 22 Mar 04 23 May 100 Khor Zubayr 2 CP R GRD/RIE 15 Mar 04 3 Jul 50 Mosil 7 CP M ME 24 Apr 04 TBD 15 Mussaibe 2 SP M (additional work) ME 28 Feb 04 20 May 200 Najaf 2 CP M ME 1 May 04 TBD 30 Nassirya 1 SP M ME 30 Mar 04 15 May 130 New Mulla 6 CP R GRD/RIE 28 Mar 04 15 May 30 Old Mulla 1 CP M ME 17 Apr 04 15 May 15 Old Mulla 2 CP M ME 17 Apr 04 15 May 15 Old Mulla 8 CP M ME 17 Apr 04 TBD 15 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 South Baghdad 1 SP M (Awaiting parts) ME 12 Feb 04 31 May 30 South Baghdad 2 SP M (Awaiting Parts) ME 12 Feb 04 31 May 30 South Baghdad 3 SP R ME 18 Mar 04 18 May 20 Taji 4 CP M GRD/RIE 21 Apr 04 15 JUL 15 Taji 7 CP R GRD/RIE 1 Oct 03 15 JUL 15 Taji 6 CP M ME 2 Apr 04 26 May 15 New In-service date LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 129 towers complete/216req’d Haditha-Baghd West 400 Sabotage GRD/RIE Complete 246 towers complete/246 req’d Hartha-Qut Wasit 400 Sabotage GRD/RIE Complete 23 Apr Operational Baiji - Baghd West #1 400 Sabotage GRD/RIE Complete Operational Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 15 Jun Dibis/Erbil-Qara Qosh 132 New Line GRD/RIE 22 May Construction ongoing Dibis to Old Kirkuk 132 Reconductor GRD-RIE 31 Jul Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE 5 Jul Assessment underway Jazair to Yarmook 132 Reconductor GRD-RIE 5 Jul Assessment underway Baghd West – Jamia 132 Sabotage ME TBD Old Amarah-Burzulgan 132 Looting GRD-RIE 25 Jun Assessment underway Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: Distribution: No report today Power transferred from North to Middle 710 MW. Power transferred from South to Middle 160 MW. GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1400 27461 1144 1471 Duhok 84 1903 79 112 Naynawa 400 7496 312 477 Tamim 160 3029 126 177 Salah Aldeen 223 4674 195 246 Anbar 195 4141 173 238 Dyala 104 2167 90 135 Babil 114 2211 92 135 Kirbala 89 1801 75 110 Najaf 119 2274 95 136 Kadsya 65 1282 53 85 Wasit 90 1946 81 122 Muthana 60 1297 54 78 Nasirya 126 2565 107 133 Misan 67 1457 61 79 Basra 350 6725 280 294 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 3 of NUMPAGES 3