System Status Jan 26

Date
26 January 2004
Category
Essential Services
Text available
English
Files
1
English original XLSDownload English text

Spreadsheet preview

Sheet “A-Steam Power Stations”: 16 rows × 13 columns

REPORT DATE - 26 January 2004
A - Steam Power Stations
Power StationsTypeNo. of UnitsNo. of Operating UnitsUnits Load (MW)Total Load MWTarget LoadRemarks
Fuel123456MW
DibisNatural Gas42881624#3 prog maint; #4 stopped at 2102 boiler leakage
BaijiFuel Oil629095185500#2 prog. maint; #4 starting; #5 forced outage; #6 prog maint
DauraFuel Oil417575180#4 rotor repair; #(5+6) Rehab
South BaghdadFuel Oil613030200#1 stopped at 1105 boiler leakage; #2 air heater defect; #3 synch at 1720; #4 stopped at 2250 vacuum pump; #5 prog maint; #6 boiler leakage
MussaibeCrude and Fuel Oil4420085150210645860#2 limited to C.W.P.; #3 boiler check
NassiryaCrude43130150150430600#4 prog maint. 28 DEC to 28 JAN.
NajebiaNatural Gas and Crude228085165160
HarthaNatural Gas and Crude419090300#1 limited to FDF; #4 prog maint
Out of Service for Unscheduled MaintanenceTotal:1,6362,824
Out of Service for Program Maintanence/Rehab
No activity
Not Performing at Peak Performance
# A-Steam Power Stations REPORT DATE - 26 January 2004 A - Steam Power Stations Power Stations Type No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load Remarks Fuel 1 2 3 4 5 6 MW Dibis Natural Gas 4 2 8 8 16 24 #3 prog maint; #4 stopped at 2102 boiler leakage Baiji Fuel Oil 6 2 90 95 185 500 #2 prog. maint; #4 starting; #5 forced outage; #6 prog maint Daura Fuel Oil 4 1 75 75 180 #4 rotor repair; #(5+6) Rehab South Baghdad Fuel Oil 6 1 30 30 200 #1 stopped at 1105 boiler leakage; #2 air heater defect; #3 synch at 1720; #4 stopped at 2250 vacuum pump; #5 prog maint; #6 boiler leakage Mussaibe Crude and Fuel Oil 4 4 200 85 150 210 645 860 #2 limited to C.W.P.; #3 boiler check Nassirya Crude 4 3 130 150 150 430 600 #4 prog maint. 28 DEC to 28 JAN. Najebia Natural Gas and Crude 2 2 80 85 165 160 Hartha Natural Gas and Crude 4 1 90 90 300 #1 limited to FDF; #4 prog maint Out of Service for Unscheduled Maintanence Total: 1636 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Report Date- 26 January 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 125 125 Gas Oil #2 lubricating oil leak from bearing Musil Dam Main 4 3 420 600 Quds 2 2 135 160 Gas Oil 37 trucks, #1 synch at 2010 Musil Dam reg 4 4 45 60 750 Mosil 12 7 11 150 29 #1 rotor defect; #2 servo + ACC; #3 stopped at 2301 bleed valve; #6 stopped at 956 diesel; #9 rotor defect Musil Pumping 2 1 110 0 Dibis 3 1 27 30 32 #4 and #5 rehab Haditha Dam 6 2 140 160 250 Old Mulla 12 7 97 128 480 #1 ACC gear, #2 servo, #5 prog maint, #10 prog maint; #12 rehab Samarra 3 2 32 55 340 New Mulla 6 3 103 173 32 #1 & #4 prog maint; #5 synch at 1350; #6 Generator defect Himrin 2 1 22 21 90 Taji 7 4 61 55 20 #3 Compressor; #4 flame def; #7 rehab Hindia 4 4 5 5 130 M. Taji 2 1 7 18 20 #2 software. Kufa 4 1 1 0 33 Daura 4 3 75 30 18 #3 Rehab Total 775 896 Hilla 4 4 68 64 22 System Generation 80350 MWh Najaf 3 2 91 129 20 #2 prog maint Syrian Line Generation 1423 MWh Khor 4 3 120 80 Natural Gas #4 rehab Turkey Line Generation 1975 MWh Shuaiba 2 1 6 20 Natural Gas #2 S/B Total Generation 83750 MWh M. Shuaiba 2 Natural Gas split with the refinery System Peak Load 3469 MW Petro 4 1 10 0 Natural Gas Syria Peak Load 60 MW M. Dibis 4 3 9 24 Natural Gas Turkey Peak Load 80 MW Mossil East 5 2 12 0 Gas Oil Fixed Gen Peak Load 127 MW Hmam/Zafranya 7 1 1 Gas Oil Total Peak Load 3736 MW Diesel 25 Gas Oil Baghdad Load 1460 MW Total 983 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Report Date - 26 January, 2004 GOVERNORATE Peak Load MW MWH Average Load MW Power transferred from North to Middle 670 MW. Power transferred from South to Middle 175 MW. Baghdad 1460 30291 1262 Duhok 80 1905 79 Naynawa 300 7700 321 Tamim 121 3172 132 Salah Aldeen 190 4608 192 Anbar 180 4011 167 Dyala 75 1937 81 Babil 85 2263 94 Kirbala 80 1960 82 Najaf 90 2455 102 Kadsya 60 1373 57 Wasit 80 1950 81 Muthana 45 1262 53 Nasirya 120 2784 116 Misan 50 1488 62 Basra 300 7193 300