DAILY POWER SYSTEM HIGHLIGHTS FOR MAY 15, 2004
The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site.
HIGHLIGHTS:
Generation:
Peak Power 4266Mw, 88,907Mw hours, 7-day Avg. 3985Mw Generators Returned to Service: (1) 100 Mw Baiji 3, SP 100 Mw
Generators Unscheduled Out of Service (13) 295 Mw PLANT
Type
SP, CP, RP, HP
Fault
Mw
Najebia 5
SP
Thrust bearing problem
80
Baiji Mobile, 4
CP
Fuel Filters
25
Doura 1,2
CP
No gas pressure
40
Mosil 2
CP
Reverse Power
15
Mosil 9
CP
Rotor Defect
15
Old Mulla 7
CP
High exhaust temp
15
* New Mulla 5
CP
Stopped to connect # 6
30
Taji 1,2,5
CP
No gas pressure
45
M. Taji 1
CP
Planned Outage
15
M. Taji 2
CP
Software
15
RED – Denotes out of service since last report
Generators Scheduled Out of Service (31) 1381 Mw PLANT
Type
SP/NG
Prog. Maintenance(M) / Rehab (R) Maint.
Org.
Date out-of -service
Est. In-service Date
Mw
Baiji 1
SP
M
Bechtel
21 Mar 04
21 May
100
Dibis 3
SP
M
ME
26 Apr 04
TBD
8
Dibis 4
SP
M
ME
15 Mar 04
TBD
8
Baiji 2
CP
M
ME
11 May 04
18 May
80
Doura 4
CP
M
ME
14 Apr 04
31 May
20
Doura 3
CP
R
ME
1 Mar 03
TBD
20
Doura 3
SP
M
ME
18 Mar 04
18 May
65
Doura 4
SP
M
ME
2 Feb 04
TBD
65
Doura 5
SP
R
Bechtel
Jul 03
20 Jun
100
Doura 6
SP
R
Bechtel
Jul 03
20 Jul
100
Dibis 4
CP
R
GRD/RIE
Sep 03
23 May
30
Hartha 1
SP
M
ME
22 Mar 04
23 May
100
Khor Zubayr 2
CP
R
GRD/RIE
15 Mar 04
3 Jul
50
Mosil 1
CP
R
GRD/RIE
24 Apr 04
11 Jun
15
Mosil 7
CP
M
ME
24 Apr 04
18 May
15
Mosil 8
CP
R
GRD/RIE
6 Feb 04
11Jun
15
Mussaibe 2
SP
M (Additional work)
ME
28 Feb 04
20 May
200
Nassirya 1
SP
M
ME
30 Mar 04
21 May
130
New Mulla 6
CP
R
GRD/RIE
28 Mar 04
23 May
30
Old Mulla 1
CP
M
GRD/RIE
17 Apr 04
15 Jun
15
Old Mulla 2
CP
M
GRD/RIE
17 Apr 04
6 Jun
15
Old Mulla 5
CP
M
GRD/RIE
17 Apr 04
6 Jun
15
Old Mulla 12
CP
R
GRD/RIE
1 Oct 03
12 Jun
15
South Baghdad 1
SP
M
ME
12 Feb 04
21 May
30
South Baghdad 2
SP
M
ME
12 Feb 04
20 May
30
South Baghdad 3
SP
R
ME
18 Mar 04
6 Jun
20
South Baghdad 5
SP
M
ME
15May 04
30 May
30
Taji 3
CP
R
GRD/RIE
6 Feb 04
23 Jul
15
Taji 4
CP
M
GRD/RIE
21 Apr 04
8 Jun
15
Taji 7
CP
R
GRD/RIE
1 Oct 03
24 JUL
15
Taji 6
CP
M
ME
2 Apr 04
26 May
15
New In-service date
LEGEND OF ELECTRICAL SYSTEM POWER SOURCE
SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER
Transmission:
LINE
Kv
Fault
Maint.
Org.
Date out-of -service
Est. In-service Date
Comments
Nassiriya-Khor Zubayr
400
Sabotage
Bechtel
26 May
159 towers complete/216req’d Haditha-Baghd West 400 Sabotage GRD/RIE
Complete
246 towers complete/246 req’d Hartha-Qut Wasit 400 Sabotage GRD/RIE
Complete
23 Apr Operational
Baiji - Baghd West #1
400
Sabotage
GRD/RIE
Complete
Operational
Baghd E.-Baghd S. #2
400
New Line
GRD/RIE
Complete
81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE
28 Feb 05
Start date 21 May 04
Baiji – Haditha
400
Sabotage
Bechtel
TBD
No contract awarded
Diyala Connection
400
New Line
ME
15 Jun
Foundations under construction Dibis/Erbil-Qara Quosh 132 New Line GRD/RIE
1 Jun
Construction ongoing
Dibis to Old Kirkuk
132
Reconductor
GRD-RIE
31 Jul
Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME
TBD
Shuwaiba-Toba-Hamar
132
Sabotage
ME
Complete
44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE
5 Jul
Assessment underway
Jazair to Yarmook
132
Reconductor
GRD-RIE
TBD
Assessment underway
Baghd West – Jamia
132
Sabotage
ME
TBD
Burzulgan-Old Amarah
132
Looting
GRD-RIE
25 Jun
Assessment underway
Temim- Tuz
132
Sabotage
ME
TBD
Nejibiya – Hartha
132
Sabotage
ME
TBD
Lines Returned to service:
Distribution: No report today Power transferred from North to Middle 750 MW.
Power transferred from South to Middle 210 MW.
GOVERNORATE
Peak Load MW
MWH
Average Load MW
Demand Load MW
Baghdad
1475
27760
1157
1425
Duhok
80
1924
80
112
Naynawa
361
8562
357
515
Tamim
155
3472
145
196
Salah Aldeen
215
4993
208
251
Anbar
185
4583
191
237
Dyala
96
2453
103
140
Babil
135
2498
104
144
Kirbala
66
1680
70
110
Najaf
125
2327
97
133
Kadsya
55
1463
61
88
Wasit
95
2132
89
121
Muthana
55
1360
57
77
Nasirya
105
2625
109
125
Misan
75
1480
62
82
Basra
290
7133
297
347
Data compiled and reported by:
LTC Tharnell M. Thomas
CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 1 of NUMPAGES 3
Home / Essential Services / ESS-03a47ff9
Essential Services
DAILY POWER SYSTEM HIGHLIGHTS FOR MAY 15, 2004