E24
ACTION NEA-00
INFO LOG- 00 CA- 00 INL-00 EB-00
TEDE-00 I0-00 L-00 NSCE-00
PER-00 PM-00 P-00 D-00
STR-00 TEST- 0 0 R-00 PMB-00
SWCI-00 /O OOW
------------------09C6A7
EUR-00 E-00
OES-00 OMB-00
SP- 00 SS0- 00
PRM- 00 G-00
UTED-00
PA-00
SS-00
SAS-00
080147Z / 62
R 071908Z APR 04
FM CPA BAGHDAD
TO SECDEF WASHDC 0474
SECSTATE WASHDC 0485
WHITE HOUSE NSC WASHDC 0467
INFO IRAQ COLLECTIVE
UNCLAS BAGHDAD 000234
SENSITIVE
E.O. 12958 : N/A
TAGS: EFIN , EINV, ETRD, EPET , IZ
SUBJECT:QCPA 900 : ADMINISTRATOR' S WEEKLY ESSENTIAL SERVICES
REPORT MAR~H 27 - APRIL 2, 2004
1 . (SBU) SUMMARY . HEADLINES OF PARAGRAPHS 3 - 9 REFLECT GOALS IN
THE COALITION PROVISIONAL AUTHORITY STRATEGIC PLAN . CPA-
WASHINGTON DISTRIBUTES ALL THREE ADMINISTRATOR' S WEEKLY REPORTS -
ESSENTIAL SERVICES, ECONOMIC , AND GOVERNANCE - WITH GRAPHICS VIA
EMAIL . THE ECONOMIC , GOVERNANCE , AND AN ABRIDGED VERSION OF THE
ESSENTIAL SERVICES REPORTS WILL BE POSTED AFTER 48 HOURS ON THE
CPA WEBSITE , WW~l.CPA-IRAQ.ORG. THE FULL ESSENTIAL SERVICES REPORT REMAINS SENSITIVE BUT UNCLASSIFIED. END SUMMARY.
2. (SBU) HIGHLIGHTS
A MARCH 28 CEREMONY TRANSFERRING AUTHORITY TO THE MINISTRY OF
HEALTH, MARKED A MILESTONE ON THE PATH TOWARD IRAQI SOVEREIGNTY.
THE TARGET OF 15 DAYS OR MORE SUPPLY FOR LIQUEFIED PETROL. EUM
GAS WAS MET IN THE SOUTH .
THE AVERAGE CRUDE OIL EXPORT FOR THE PAST 30 DAYS WAS 1 . 852
MILLION BARRELS PER DAY (MBPD) , OR 112% OF THE COALITION
PROVISIONAL AUTHORITY'S (CPA) NEW GOAL OF 1 . 6 MPBD, SET THIS PAST
WEEK .
PROVIDE ELECTRICITY SERVICES THAT MEET NATIO NAL NEEDS
3. (SBU) CPA TASKS : IMPROVE GENERATING CAPACITY TO 6000 MW BY
JUNE 1, 2004; FULLY IMPLEMENT POLICY ON ALLOCATION OF ELECTRICAL
POWER ; PUBLISH DRAFT OF LONG TERM STRATEGY ; MINIMIZE SABOTAGE AND
IMPROVE SECURITY
THE SEVEN-DAY AVERAGE (MARCH 27-APRIL 2) OF PEAK ELECTRICITY
PRODUCTION WAS 3,883 MW , A DECREASE OF 5 . 2 PERCENT FROM THE
PREVIOUS WEEK . THE PRINCIPAL REASON FOR THIS DECREASE IS
SCHEDULED MAINTENANCE FOR SPRING. THE UNITS UNDERGOING REPAIR
SHOULD ALL BE OPERATIONAL BY MID MAY. ON MARCH 27, PEAK
PRODUCTION HIT A HIGH FOR THE WEEK AT 4,103 MW.
EIGHT (400 KV) AND TEN (132 KV) TRANSMISSION LINES ARE
CURRENTLY OUT OF SERVICE. HOWEVER, EXISTING TRANSMISSION CAPACITY
IS SUFFICIENT TO COMPENSATE FOR DOWNED LINES .
THE SEVEN-DAY AVERAGE (MARCH 27-APRIL 2) PRODUCTION OF
ELECTRICAL ENERGY WAS 82,391 MWH PER DAY, A DECREASE OF 6 PERCENT
FROM THE PREVIOUS WEEK. AGAIN, THIS IS DUB TO SCHEDULED
MAINTENANCE. ON MARCH 27, THE PRODUCTION OF ELECTRICAL ENERGY
PEAKED FOR THE WEEK AT 87,126 MWH.
THE FOLLOWING CHART PRESENTS THE DAILY ELECTRIC POWER
CONSUMPTION BROKEN DOWN AMONG THE NORTH, CENTRAL (INCLUDING
BAGHDAD) , AND SOUTH REGIONS. DURING THE REPORTING PERIOD , THE
NORTH CONSUMED AN AVERAGE OF 867 MW PER DAY , OR 24 PERCENT OF
TOTAL POWER CONSUMPTION. PER DAY, THE CENTRAL REGION CONSUMED
2, 157 MW , OR 60 PERCENT OF THE TOTAL, AND THE SOUTH CONSUMED 594
MW, OR 16 PERCENT OF TOTAL ELECTRICITY CONSUMPTION DURING THE PAST
WEEK.
RECONSTRUCT COMMUNICATIONS AND POSTAL SYSTEMS
4. (SBU) CPA TASKS: BUILD IRAQ'S FIRST RESPONDER NETWORK;
ESTABLISH INDEPENDENT REGULATORY AGENCY; UPGRADE IRAQI TELEPHONE
AND POSTAL COMPANY (ITPC) NETWORK FOR INTEROPERABILITY; BUILD
TRANSMISSION COMPONENT DATA NETWORK FOR IRAQ, INCLUDING
INTERNATIONAL GATEWAYS ; RESTRUCTURE ITPC AND ITS BUSINESS
OPERATIONS ; UPGRADE AND MODERNIZE POSTAL SYSTEMS ; UPGRADE ITPC
OUTSIDE PLANT FOR INCREASED SUBSCRIBER CAPACITY AND USE
SINCE MAY 2003, CPA HAS REINSTATED LANOLINE TELEPHONE SERVICE
FOR 160 ,654 SUBSCRIBERS , INCLUDING 12 ,933 SINCE LAST WEEK . CPA
CONTINUES TO MAKE PROGRESS IN RESTORING SERVICE TO CUSTOMERS ,
ESPECIALLY IN BAGHDAD .
THE FOLLOWING PARAGRAPHS DELINEATE THE NUMBER OF LANOLINE AND
CELL PHONE SUBSCRIBERS IN IRAQ, AND COMPARE THEM TO PRE-WAR
ESTIMATES . THE CHART BELOW SHOWS THE NUMBER OF ACTIVE LANOLINE
SUBSCRIBERS IN APRIL 2003 , THE CURRENT NUMBER OF ACTIVE LANOLINE
SUBSCRIBERS, THE NUMBER OF LANOLINE SUBSCRIBERS REINSTATED POST-
CONFLICT (SINCE MAY 2003) , AND THE NUMBER OF FORMERLY ACTIVE
LANOLINE SUBSCRIBERS WHO REMAIN WITHOUT SERVICE (EXCLUDING THE
THREE NORTHERN GOVERNORATES .
THE THREE NEW CELL PHONE COMPANIES IN IRAQ (ASIA CELL , IRAQNA,
AND ATHEER IN THE NORTH , CENTRAL, AND SOUTH RESPECTIVELY) CONTINUE
TO ENROLL NEW CELL PHONE SUBSCRIBERS. CURRENTLY , IN MOSUL,
SULAYMANIYAH , AND KIRKUK, THERE ARE 146,210 CELL PHONE
SUBSCRIBERS . IN BAGHDAD, THERE ARE 135,000 CELL PHONE
SUBSCRIBERS; AND IN BASRA, AL KUT, AMARAH, SAMAWAH, AND NASIRIYAH
THERE ARE 40,000 CELL PHONE SUBSCRIBERS.
CURRENTLY, THERE ARE 743,254 ACTIVE LANOLINE TELEPHONE
SUBSCRIBERS IN IRAQ, COMPARED TO 833, 000 SUBSCRIBERS PRE-WAR. THE
TOTAL NUMBER OF TELEPHONE SUBSCRIBERS IN IRAQ, INCLUDING THE CELL
PHONE SUBSCRIBERS, IS 1,064,464, WHICH IS 27.9 PERCENT GREATER
THAN THE NUMBER OF ACTIVE LANOLINE SUBSCRIBERS PRE-WAR. THERE WAS
NO PRE-WAR CELL PHONE SERVICE.
THE PENETRATION RATE (THE NUMBER OF ACTIVE LANOLINE TELEPHONE
SUBSCRIBERS AS A PERCENTAGE OF THE POPULATION) IS 2 . 8 PERCENT
(USING AN ESTIMATED POPULATION OF 25.9 MILLION).
THE FOLLOWING CHART SHOWS THE PERCENTAGE OF OPERATIONAL
TELEPHONE SUBSCRIBERS COMPARED TO THE NUMBER OF ACTIVE SUBSCRIBERS
IN APRIL 2003. THE PERCENTAGE OF ACTIVE SUBSCRIBERS IN BAGHDAD
INCREASED BY THREE PERCENTAGE POINTS FROM LAST WEEK.
PROVIDE FOOD SECURITY FOR ALL IRAQIS
5. (SBU) CPA TASKS: ENHANCE CAPACITY OF MINISTRY OF AGRICULTURE;
ASSURE SUPPLY OF INPUTS; STRENGTHEN RESEARCH SYSTEM; ENSURE
ADEQUATE STOCKS FOR PUBLIC DISTRIBUTION SYSTEM (PDS) ; MONITOR FOOD
SECURITY ; HAND OVER ADMINISTRATION OF SYSTEM IN THE NORTH;
INITIATE REFORM OF RATIONS BASKET; ENVIRONMENTAL INITIATIVES
THE FOLLOWING CHART SHOWS THE PERCENTAGE OF ESTIMATED
REQUIREMENTS OF STOCKS FOR THE 12 PUBLIC DISTRIBUTION GOODS THAT
IRAQIS RECEIVE UNDER THE PDS UNTIL THE END OF MAY . THE PERCENTAGE
OF ESTIMATED REQUIREMENTS CATEGORIZED INTO OPENING STOCKS (AMOUNT
ON HAND) , SCHEDULED ARRIVALS UNDER EXISTING CONTRACTS FROM THE OIL
FOR FOOD PROGRAM , SCHEDULED ARRIVALS OF GOODS FROM CONTRACTS
ARRANGED BY THE MINISTRY OF TRADE (MOT) , AND SCHEDULED ARRIVALS OF
GOODS FROM NEW CONTRACTS ARRANGED BY THE WORLD FOOD PROGRAM (WFP) .
THE PDS STOCKS IN THE FOLLOWING CHART ARE CALCULATED AS A
PERCENTAGE OF TWO MONTHS (APRIL-MAY) ESTIMATED DEMAND, PLUS A ONE-
MONTH BUFFER STOCK (CPA GO AL BY MAY) . HAVING 100 PERCENT OF EACH
COMMODITY WILL ENSURE THAT THE FOOD RATIONS ARE AVAILABLE THROUGH
MAY , INCLUDING AT LEAST A ONE-MONTH ON HAND BUFFER STOCK FOR EACH
COMMODITY.
NOTE : OIL FOR FOOD UNCONFIRMED CONTRACTS ARE THOSE CONTRACTS
FOR WHICH A VALID LETTER OF CREDIT EXISTS BUT NO SHIPPING
DOCUMENTATION HAS YET BEEN RECEIVED BY THE OIL FOR FOOD
COORDINATION CENTER .
CPA PROJECTS THAT NO SHORTAGES WILL OCCUR IN THE APRIL AND MAY
RATIONS GIVEN THE NEW PROCUREMENTS OF FOOD BASKET COMMODITIES BY
BOTH WFP AND MOT, INCLUDING ACCELERATED DELIVERY SCHEDULES FOR THE
COMMODITIES WHERE STOCKS HAVE BEEN LOW. HOWEVER, MOT FACES
PROBLEMS IN PROVIDING UPDATED, ACCURATE PDS INFORMATION ON A
WEEKLY BASIS.. THESE PROBLEMS STEM FROM DIFFICULT COMMUNICATIONS
LINKS BETWEEN THE GOVERNORATES AND BAGHDAD , AS WELL AS THE NEED TO
UPGRADE INVENTORY CONTROL PROCEDURES. CPA IS WORKING ON THESE
CHALL. ENGES AS PART OF ITS HANDOVER STRATEGY . PULSES ARE EXPECTED
TO CONTINUE TO DECLINE BECAUSE OF THE WARMING MONTHS AHEAD MAKING
IT MORE DIFFICULT TO STORE THEM FOR EXTENDED PERIODS. THEY WILL
BE REPLACED BY TOMATO PASTE AND CANNED CHEESE .
THE FOLLOWING CHART SHOWS THE CURRENT PDS STOCKS AND SCHEDULED
ARRIVALS AS A PERCENTAGE OF TOTAL REQUIREMENTS FROM APRIL UNTIL
TRANSITION ON JULY 1 . CPA 'S GOAL IS TO PROVIDE SUFFICIENT RATION
STOCKS FOR JULY , PLUS A THREE MONTH BUFFER. ON THE GRAPH BELOW,
100 PERCENT OPENING STOCKS IN EACH COMMODITY CATEGORY INDICATES
THAT THIS GOAL HAS BEEN ACHIEVED .
WFP HAS COMPLETED ITS PROCUREMENT SCHEDULE AS OF APRIL 1 . ALL
PLANNED WFP PROCUREMENT IS REFLECTED IN THE CHART .
NOTE: THE MINISTRY OF TRADE IS ANTICIPATING SUBSTANTIAL
TONNAGE OF FOREIGN WHEAT IN THE COMING MONTHS.
IMPROVE QUALITY AND ACCESS TO HEALTHCARE
6. (SBU) CPA TASKS: DEVELOP HEALTH CARE ORGANIZATIONS,
MANAGEMENT , AND INFRASTRUCTURE ; TRAIN HEALTH CARE PROFESSIONALS;
SECURE SYSTEM; PUBLIC HEALTH ; PHARMACEUTICALS LOGISTIC SUPPORT ;
STRATEGIC COMMUNICATIONS
A MARCH 28 CEREMONY TRANSFERRING AUTHORITY TO THE MINISTRY OF
HEALTH , MARKED A MILESTONE ON THE PATH TOWARD IRAQI SOVEREIGNTY.
LOCAL GOVERNANCE PROGRAM (LGP) PARTICIPATED IN THE
DISTRIBUTIO N OF 4 , 000 POSTERS AND 2 , 000 TEACHING FOLDERS INFORMING
THE PEOPLE OF NAJAF ABOUT THE "MEASLES VACCINATION CAMPAIGN ,"
WHICH AIMS TO DECREASE THE NUMBER OF CASES OF INFECTED SCHOOL
CHILDREN . LGP ANTICIPATES THAT THE ADVERTISING WILL SIGNIFICANTLY
INCREASE THE NUMBER OF VACCINATED CHILDREN.
IMPROVE QUALITY AND ACCESS TO EDUCATION
7 . (SBU) CPA TASKS: REORGANIZE AND STAFF THE MINISTRY OF
EDUCATION; REHABILITATE SCHOOL BUILDINGS AND BUILD NEW SCHOOLS;
ADVANCE NATIONAL DIALOGUE ON CURRICULUM REFORM; CONTINUE AND
EXPAND TEACHER TRAINING
THE EDUCATION MINISTER HOSTED THE SECOND NATIONAL CONFERENCE
ON CURRICULUM REFORM MARCH 30-31. IT WAS ATTENDED BY OVER 250
LEADERS REPRESENTING THE EDUCATION , BUSINESS, CIVIC , RELIGIOUS AND
POLITICAL SECTORS OF IRAQI SOCIETY. FOUR MEMBERS OF THE IRAQI
GOVERNING COUNCIL ATTENDED , AS DID OTHER MINISTRY REPRESENTATIVES.
THE CONFERENCE PRODUCED A FRAMEWORK AND PROCESS FOR CURRICULUM
REFORM THAT WILL BE IMPLEMENTED OVER THE NEXT TWO TO THREE YEARS .
THE MINISTRY OF EDUCATION (MOE) LAUNCHED ITS EDUCATION
MANAGEMENT INFORMATION SYSTEM - A TOOL TO REBUILD A COMPREHENSIVE
SCHOOL DATA PROFILE , INCLUDING , BUT NOT LIMITED TO, THE NUMBER OF
STUDENTS , ACADEMIC RECORDS, BUILDING SIZE AND DAMAGE REPORTS .
RECORDS OF THIS NATURE WERE DESTROYED AFTER THE FALL OF THE PAST
REGIME . THIS SYSTEM IS THE FIRST CRITICAL TOOL THE MINISTRY NEEDS
FOR USING DATA IN DECISION MAKING.
RESTORE ECONOMICALLY - STRATEGIC TRANSPORTATION INFRASTRUCTURE
8. (SBU) CPA TASKS: ENABLE IRAQI CIVIL AVIATION TO PREPARE FOR
INTERNATIONAL COMMERCIAL AVIATION AND CARGO SERVICE ; ENABLE IRAQI
PORT AUTHORITY (IPA) TO ADMINISTER A PORT OF CALL WITH INTERMODAL
CAPABILITIES AND INLAND CONTAINER DISTRIBUTION ; ENABLE IRAQI
RAILROAD RAILWAYS ( IRR) TO PROVIDE DOMESTIC AND INTERNATIONAL
PASSENGER AND FREIGHT CAPABILITIES; REFORM CIVIL SERVICE AT
MINISTRY OF TRANSPORTATION
THE CPA MINISTRY OF TRANSPORTATION (MOT) TEAM COMPLETED THE
FIRST QUARTER REPORT ON SUPPLEMENTAL FUNDING FOR THE MINISTRY .
THE REPORT PROVIDED AN UPDATE ON THE $365 MILLION BUDGETED TO
SUPPORT THE PORTS , AVIATION , AND RAILROAD SECTORS .
REPRESENTATIVES OF THE MOT AVIATION TEAM MET WITH THE AIR
TRAFFIC CELL HEAD AT THE COMBINED AIR OPERATIONS CENTER (CAOC) IN
AL-UDEID TO DISCUSS CO NTINUING ADJUSTMENTS TO THE AVIATION
TRANSITION PLAN DURING THE BAGHDAD INTERNATIONAL AIRPORT(BIAP)
DRAWDOWN. DURING THIS DISCUSSION , THE TEAM UPDATED THE AIR
TRAFFIC CELL O N THE CURRENT PROJECTED TIMELINES FOR ESTABLISHING A
CIVIL CAPABILITY - I.E. IRAQI CIVIL AVIATIO N AUTHORITY (CAA)
PERHAPS AUGMENTED BY EXTERNAL RESOURCES SUCH AS CONTRACTORS - TO
ASSUME RESPONSIBILITY FOR A VARIETY OF BIAP AIR TRAFFIC MANAGEMENT
(ATM) FUNCTIONS AND THE AREA CONTROL CENTER (ACC) WHICH W OULD
CONTROL CIVIL ROUTES THROUGH IRAQI AIRSPACE .
THE NORTH PORT OF UMM QASR IS NOW POWERED FROM THE GRID .
GENERATORS ARE STILL AVAILABLE FOR BACKUP POWER IF NEEDED .
ADDITIONALLY , THE IRAQ PORT AUTHORITY (IPA) STARTED LAYING CABLE
TO CONNECT THE SOUTH PORT TO THE GRID . THIS WILL INCREASE
CONTAINER CRANE CAPACITY AND REDUCE FUEL COSTS SINCE GENERATORS
CAN NOW BE USED AS BACKUPS.
A MEETING REGARDING THE WATER SITUATION AT UMM QASR, ORGANIZED
BY THE OFFICE OF THE CHIEF OPERATING OFFICER, RESULTED IN
PROCEDURES TO OFFICIALLY TRANSFER RESPONSIBILITY FOR WATER SUPPLY
TO UMM QASR FROM THE MOT TO THE MINISTRY OF MUNICIPALITIES AND
PUBLIC WORKS .
RECONSTITUTE OIL INFRASTRUCTURE
9 . (SBU) CPA TASKS: PRODUCTION/EXPORTS ; PRODUCT SUPPLY ;
SECURITY ; STRUCTURAL REFORM
THE GRAPH BELOW SHOWS THE DAILY CRUDE OIL PRODUCTION IN IRAQ
OVER THE PAST NINE MONTHS. THE DASHED BLACK LINE IS THE CURRENT
PRODUCTION TARGET GOAL OF 2 MILLION BARRELS PER DAY (MBPD) . FOR
THE WEEK OF MARCH 27 - APRIL 2, THE ESTIMATED AVERAGE TOTAL CRUDE
OIL PRODUCTION WAS 2.434 MBPD (1.95 MBPD IN THE SOUTH AND 0 . 48
MBPD IN THE NORTH). THE AVERAGE CRUDE OIL EXPORT FOR THE PAST 30
DAYS WAS 1 . 75 MBPD . THE AVERAGE PRICE RECEIVED FOR CRUDE OIL
EXPORTS THIS YEAR IS APPROXIMATELY $26 PER BARREL .
ON APRIL 1 , THE CRUDE OIL PRODUCTION GOAL INCREASED TO 2. 5
MBPD AND THE EXPORT GOAL INCREASED TO 1 . 6 MBPD . THESE NUMBERS
WILL BE REFLECTED IN FUTURE REPORTS .
LIQUEFIED PETROLEUM GAS (LPG) PRODUCTION DROPPED AFTER THE
NORTH GAS PLANT WENT DOWN FOR MAINTENANCE . THE PLANT IS PROJECTED
. . .
TO BE BACK IN PRODUCTION BY APRIL 1.
THE FOLLOWING TABLE SHOWS THE FOUR MAIN FUELS IN IRAQ (DIESEL ,
KEROSENE I LIQUEFIED PETROLEUM GAS I AND GASOLINE) I THE ESTIMATED
TOTAL NATIO NAL DAILY DEMAND FOR EACH , AND THE PERCENTAGE OF FUEL
SUPPLY THAT IS O N HAND (WEEKLY AVERAGE) OUT OF TOTAL DEMAND .
--ON APRIL 1 , ALL THE ESTIMATED DAILY DEMAND FO R ALL FUELS
CHANGED . GASOLINE INCREASED TO 19 ML FROM 17 ML ; LPG DEMAND
DECREASED TO 4500 METRIC TONS FROM 5500 METRIC TO NS ; KEROSENE
DEMAND DECREASED TO 6 ML FROM 9 ML ; DIESEL DEMAND INCREASED . 5 ML
TO 18.5 ML .
THE GRAPH BELOW SHOWS THE TOTAL DAILY SUPPLY (DOMESTIC
PRODUCTION PLUS IMPORTS) FOR EACH OF THE FOUR REFINED FUEL
PRODUCTS AS A PERCENTAGE OF ESTIMATED DOMESTIC DEMAND OVER THE
PAST SIX MONTHS . A RECENT REDUCTION IN THE ESTIMATED DAILY DEMAND
FOR KEROSENE EXPLAINS THE SPIKE IN MARCH. DOMESTIC PRODUCTION OF
KEROSENE WILL EXCE. ED DEMAND AS WARMER WEATHER CONTINUES 1 AND LEAD
TO REDUCED IMPORT REQUIREMENTS.
THE CHART BELOW SHOWS THE DAYS OF SUPPLY ON HAND AS OF APRIL 2
FOR EACH OF THE FOUR MAIN FUEL PRODUCTS IN IRAQ . CPA ' S GOAL
REMAINS TO HAVE 15 DAYS OF SUPPLY (DOS) ON HAND FOR EACH FUEL
SOURCE IN EVERY REGION. THIS WEEK , THE NORTH, BAGHDAD 1 SOUTH , AND
SOUTH CENTRAL MET THE 15 DOS TARGET FOR KEROSENE . THE SOUTH MET
ITS TARGET FOR LPG .
BREMER
NNNN
Home / US Department of Defense records / DOD-1e0a1f5e
US Department of Defense records
08-F-0984 E24
- Date
- 2 April 2004
- Category
- US Department of Defense records
- Text available
- English
- Source
- US Department of Defense — FOIA reading room (Internet Archive)
Highlighting search results for: